Question

In: Accounting

On February 1, 2020, a company agreed to construct a building at a contract price of...

On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:

                                                    2020             2021           2022

Total costs incurred to date        $8,000        $10,000         $22,000

Estimated costs to complete      12,000          6,000            -0-

Customer billings to date           8,000          24,000         29,000

Collections to date                     4,000           14,000         25,000

The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.

Solutions

Expert Solution

I'm really sorry, I misread the question and I'm editing the answer to make it easy for you, rather than solving in the comments.

The amount to be booked as Billings on construction in process shall be calculated in the following manner

Total Revenue of Contract is - 35,000$

As on 2021, Total Work Completed is 10,000 and estimated expense to completion is 6,000$ which means 62.5% of the work is done and accordingly 62.5% of the revenue should also be recorded.

So therefore, 62.5% of 35,000$ is $21,875.

Billings done earlier is 8,000$, therefore balance of 13,875$ should be the billings to be recorded in the current year i.e. 2021.

The answer is $ 13,875.

I am really sorry once again and hope this answer satisfies your purpose.

I hope the above solution is what you were looking for. For any further queries or doubts in the solution, please feel free to drop a comment. Please do leave a positive feedback, Thank you :


Related Solutions

On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $8,000 $10,000 $22,000 Estimated costs to complete 12,000 6,000 -0- Customer billings to date 9,000 21,000 29,000 Collections to date 4,000 14,000 25,000 If the company uses the percentage-of-completion method, an inventory/current...
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400. Joe estimated total construction costs would be $12,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                                              2020                       2021                      2022        Total costs incurred to date                                        $4,500                    $7,920                  $13,800 Estimated costs to complete                                         7,500                      5,280                     -0- Customer billings to date                                             6,600                    12,000                    16,800 Collections to date                                                      6,000                    10,500                    16,500 Instructions: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000 Instructions Fill in...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below. 2020 2021 2022 Actual costs incurred during each individual year $10,000,000 15,000,000 12,500,000...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT