Question

In: Accounting

On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...

On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000

Instructions Fill in the correct amounts on the following schedule.For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2010, 2011, and 2012.

Percentage-of-Completion Revenue

2010:

2011:

2012:

Completed-Contract Revenue

2010:

2011:

2012:

Percentage-of-Completion Gross Profit

2010:

2011:

2012:

Completed-Contract Gross Profit

2010:

2011:

2012:

Calculate the Over/Under Billing for:

2010:

2011:

2012:

Solutions

Expert Solution

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Marsh contractor
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2010 $1,500,000 $1,500,000 $4,000,000 37.50% $5,800,000 $2,175,000 $2,175,000 $675,000
2011 $1,140,000 $2,640,000 $4,400,000 60.00% $5,800,000 $3,480,000 $1,305,000 $165,000
2012 $1,960,000 $4,600,000 $4,600,000 100.00% $5,800,000 $5,800,000 $2,320,000 $360,000
Computation of Gross Profit - Revenue on completion - Marsh contractor
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2010 $1,500,000 $1,500,000 $4,000,000 $5,800,000 $0
2011 $1,140,000 $2,640,000 $4,400,000 $5,800,000 $0
2012 $1,960,000 $4,600,000 $4,600,000 $5,800,000 $1200,000

Please give thumbs up :-)


Related Solutions

On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          24,000         29,000 Collections to date                     4,000           14,000         25,000 The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $8,000 $10,000 $22,000 Estimated costs to complete 12,000 6,000 -0- Customer billings to date 9,000 21,000 29,000 Collections to date 4,000 14,000 25,000 If the company uses the percentage-of-completion method, an inventory/current...
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400. Joe estimated total construction costs would be $12,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                                              2020                       2021                      2022        Total costs incurred to date                                        $4,500                    $7,920                  $13,800 Estimated costs to complete                                         7,500                      5,280                     -0- Customer billings to date                                             6,600                    12,000                    16,800 Collections to date                                                      6,000                    10,500                    16,500 Instructions: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here. Cost incurred till Dec.31, 2013 $1,080,000 Billings made to City $1,000,000 Amount collected from City $ 750,000 The estimated future cost to complete this contract is $3,240,000. (a) Prepare Chicago contractors 2013 journal entries using COMPLETED CONTRACT method. (b) Show how the contract accounts will appear in...
Red Builders agrees to construct a new building for Blue Co. for a total contract price...
Red Builders agrees to construct a new building for Blue Co. for a total contract price of $6,000,000. The estimated construction costs at inception was $4,000,000. The construction project was completed after two years. Below are the actual costs for years 1 and 2: Description Cumulative Year 1 Year 2 Cost incurred to date 1,200,000 2,500,000 Estimated additional costs to complete 3,600,000 2,100,000 Billings 1,050,000 2,300,000 Cash Collections 1,000,000 1,900,000 Red has determined that this contract qualifies for revenue recognition...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in terms of which the construction company undertook to build one Medical Suite Block, consisting of 50 suites of 3 rooms, a waiting room, Doctors consulting room, reception area and kitchenette. The contract stipulated that the building would be completed by 15 December 2015. The contracting parties also agreed to the following: a) If the hostels are not completed by 15 December 2015, Build-IT Building...
McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $1,500,000 $1,300,000 Estimated costs to complete 1,200,000 0 Billings during the year 1,200,000 1,300,000 Cash collections during the year 1,000,000 1,500,000 Part 1: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT