In: Accounting
Contract Price | $42,000 | |||||||||||||||
A | B | C=A+B | D=(A/C)*100% | E=D*42000 | ||||||||||||
End of Year | Cost Incurred during the Year | Actual Cost to date | Estimated further cost | Total Estimated Cost | Percentage Completion | Cumulative Recognized Revenue | Recognized during the year | |||||||||
2020 | $8,000 | $8,000 | $12,000 | $20,000 | 40.0% | $16,800 | $16,800 | |||||||||
2021 | $2,000 | $10,000 | $6,000 | $16,000 | 62.5% | $26,250 | $9,450 | |||||||||
2022 | $12,000 | $22,000 | $0 | $22,000 | 100.0% | $42,000 | $15,750 | |||||||||
Year | ConstructionRevenue | Construction Expense | Gross Profit/(Loss) | |||||||||||||
2020 | $16,800 | $8,000 | $8,800 | |||||||||||||
2021 | $9,450 | $2,000 | $7,450 | |||||||||||||
2022 | $15,750 | $12,000 | $3,750 | |||||||||||||
As on December 31,2021 | ||||||||||||||||
Cumulative expenses | $10,000 | |||||||||||||||
Cumulative Revenue | $26,250 | |||||||||||||||
Billing to date | $21,000 | |||||||||||||||
Collection to date | $14,000 | |||||||||||||||
Accounts | Debit | Credit | ||||||||||||||
Construction in progress | $16,250 | |||||||||||||||
Construction Expense | $10,000 | |||||||||||||||
Construction Revenue | $26,250 | |||||||||||||||
Accounts Receivable | $21,000 | |||||||||||||||
Billing on construction contract | $21,000 | |||||||||||||||
Cash | $14,000 | |||||||||||||||
Accounts Receivable | $14,000 | |||||||||||||||
If the company uses the percentage-of-completion method, an inventoryof $16,250 should be shown on the balance sheet at December 31, 2021 related to the project. | ||||||||||||||||
Related SolutionsOn February 1, 2020, a company agreed to construct a building at a contract price of...On February 1, 2020, a company agreed to construct a building at
a contract price of $35,000. The company estimated the project
would be finished in 2022. Information relating to the costs and
billings for this contract is as follows:
2020 2021 2022
Total costs incurred to
date $8,000 $10,000 $22,000
Estimated costs to
complete 12,000 6,000 -0-
Customer billings to
date 8,000 24,000 29,000
Collections to
date 4,000 14,000 25,000
The journal entry to record Billings on
Construction in Process in 2021 has the amount of
_________.
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....On February 1, 2020, Joe agreed to construct a building at a
contract price of $17,400. Joe estimated total construction costs
would be $12,000 and the project would be finished in 2022.
Information relating to the costs and billings for this contract is
as follows:
2020 2021 2022
Total costs incurred to
date $4,500 $7,920 $13,800
Estimated costs to
complete 7,500 5,280 -0-
Customer billings to
date 6,600 12,000 16,800
Collections to
date 6,000 10,500 16,500
Instructions:
Fill in the correct amounts on the following schedule. For
percentage-of-completion accounting and for completed-contract
accounting, show...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a
building at a contract price of $3,000,000. Marcos estimated total
construction costs would be $2,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows:
? 2010?? 2011?? 2012?
Total costs incurred to date?$
750,000?$1,320,000?$2,300,000
Estimated costs to complete?1,250,000? 880,000?-0-
Customer billings to date?1,100,000? 2,000,000?3,000,000
Collections to date?1,000,000? 1,750,000?2,950,000
Instructions
1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...On February 1, 2010, Marcos Contractors agreed to construct a
building at a contract price of $3,000,000. Marcos estimated total
construction costs would be $2,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows:
? 2010?? 2011?? 2012?
Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000
Estimated costs to complete?1,250,000? 880,000?-0-
Customer billings to date?1,100,000? 2,000,000?3,000,000
Collections to date?1,000,000? 1,750,000?2,950,000
Instructions
1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...On February 1, 2010, Marsh Contractors agreed to construct a
building at a contract price of $5,800,000. Marsh estimated total
construction costs would be $4,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows: 2014 2015 2016 Total costs
incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs
to complete 2,500,000 1,760,000 -0- Customer billings to date
2,200,000 4,000,000 5,600,000 Collections to date 2,000,000
3,500,000 5,500,000
Instructions Fill in...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...On January 1, 2018, Grumpy Contractors agreed to construct a
building at a contract price of $5,000,000. Grumpy estimates that
the project will be finished in 2020. Information related to the
costs and billings for this contract are as follows:
2018
2019
2020
Total costs incurred to date
$1,500,000
$3,300,000
$4,400,000
Estimated costs to complete
2,500,000
1,000,000
-0-
Customer billings to date
1,200,000
2,700,000
4,400,000
Collections to date
1,000,000
2,500,000
4,400,000
Instructions:
Assuming the building was finished in 2020, calculate...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer. The...In 2020 Coco Corporation signed a contract to construct a major
office building for a developer. The construction is
expected to take 3 years. The contract price is $50
million. The actual costs incurred each year, the
estimated costs of completing the project as of the end of each
year, the progress billings for each year, and the collections of
those billings each year are presented in the chart below.
2020
2021
2022
Actual costs incurred during each individual
year
$10,000,000
15,000,000
12,500,000...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...Splish, Inc. began work on a $6,312,000 contract in 2020 to
construct an office building. During 2020, Splish, Inc. incurred
costs of $1,589,940, billed its customers for $1,156,000, and
collected $894,000. At December 31, 2020, the estimated additional
costs to complete the project total $3,228,060.
Prepare Splish’s 2020 journal entries using the
percentage-of-completion method. (Credit account titles
are automatically indented when amount is entered. Do not indent
manually. For costs incurred use account Materials, Cash, Payables.
If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...Crane, Inc. began work on a $7,016,000 contract in 2020 to
construct an office building. During 2020, Crane, Inc. incurred
costs of $1,798,560, billed its customers for $1,125,000, and
collected $910,000. At December 31, 2020, the estimated additional
costs to complete the project total $3,197,440.
Prepare Crane’s 2020 journal entries using the
percentage-of-completion method. (Credit account titles
are automatically indented when amount is entered. Do not indent
manually. For costs incurred use account Materials, Cash, Payables.
If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...Stellar, Inc. began work on a $6,491,000 contract in 2020 to
construct an office building. During 2020, Stellar, Inc. incurred
costs of $1,941,020, billed its customers for $1,138,000, and
collected $904,000. At December 31, 2020, the estimated additional
costs to complete the project total $3,304,980.
Prepare Stellar’s 2020 journal entries using the
percentage-of-completion method. (Credit account titles
are automatically indented when amount is entered. Do not indent
manually. For costs incurred use account Materials, Cash, Payables.
If no entry is...
ADVERTISEMENT
ADVERTISEMENT
Latest Questions
ADVERTISEMENT
|