In: Accounting
Question 25
On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $5,940,000. Marsh estimated total construction costs would be $4,112,000 and the project would be finished in 2019. Information relating to the costs and billings for this contract is as follows:
2017 | 2018 | 2019 | ||||
Total costs incurred to date | $1,542,000 | $2,724,000 | $4,670,000 | |||
Estimated costs to complete | 2,570,000 | 1,816,000 | -0- | |||
Customer billings to date | 2,340,000 | 4,112,000 | 5,740,000 | |||
Collections to date | 2,140,000 | 3,640,000 | 5,640,000 |
Fill in the correct amounts on the following schedule. For
percentage-of-completion accounting and for completed-contract
accounting, show the gross profit that should be recorded for 2017,
2018, and 2019.