In: Finance
Hampton Manufacturing estimates that its WACC is 12.4%. The company is considering the following seven investment projects:
Project | Size | IRR | |||
A | $ 700,000 | 14.5 | % | ||
B | 1,250,000 | 14.0 | |||
C | 1,250,000 | 13.4 | |||
D | 1,250,000 | 13.2 | |||
E | 700,000 | 12.9 | |||
F | 700,000 | 12.3 | |||
G | 1,000,000 | 12.2 |
Project A | -Select-acceptdon't acceptItem 1 |
Project B | -Select-acceptdon't acceptItem 2 |
Project C | -Select-acceptdon't acceptItem 3 |
Project D | -Select-acceptdon't acceptItem 4 |
Project E | -Select-acceptdon't acceptItem 5 |
Project F | -Select-acceptdon't acceptItem 6 |
Project G | -Select-acceptdon't acceptItem 7 |
What is the firm's optimal capital budget? Write out your answer
completely. For example, 13 million should be entered as
13,000,000. Round your answer to the nearest dollar.
$
Project A | -Select-acceptdon't acceptItem 9 |
Project B | -Select-acceptdon't acceptItem 10 |
Project C | -Select-acceptdon't acceptItem 11 |
Project D | -Select-acceptdon't acceptItem 12 |
Project E | -Select-acceptdon't acceptItem 13 |
Project F | -Select-acceptdon't acceptItem 14 |
Project G | -Select-acceptdon't acceptItem 15 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000. Round your answer to the nearest
dollar.
$
Project A | -Select-acceptdon't acceptItem 17 |
Project B | -Select-acceptdon't acceptItem 18 |
Project C | -Select-acceptdon't acceptItem 19 |
Project D | -Select-acceptdon't acceptItem 20 |
Project E | -Select-acceptdon't acceptItem 21 |
Project F | -Select-acceptdon't acceptItem 22 |
Project G | -Select-acceptdon't acceptItem 23 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000. Round your answer to the nearest
dollar.
$
Project | Size | IRR | ||
A | 700,000 | 14.50% | ||
B | 1,250,000 | 14.00% | ||
C | 1,250,000 | 13.40% | ||
D | 1,250,000 | 13.20% | ||
E | 700,000 | 12.90% | ||
F | 700,000 | 12.30% | ||
G | 1,000,000 | 12.20% | ||
The projects whose return i.e. IRR is greater than the cost of capital should be accepted | ||||
Project | Decision | |||
A | Accept | |||
B | Accept | |||
C | Accept | |||
D | Accept | |||
E | Accept | |||
F | Reject | |||
G | Reject | |||
Optimal Capital Budget | 5,150,000 | |||
b.The project with higher NPV should be selected | ||||
Project | Decision | |||
A | Accept | |||
B | Accept | |||
C | Reject | |||
D | Accept | |||
E | Accept | |||
F | Reject | |||
G | Reject | |||
Optimal Capital Budget | 3,900,000 | |||
c. | ||||
Project | Size | IRR | Required return | Decision |
A | 700,000 | 14.50% | 14.4 | Accept |
B | 1,250,000 | 14.00% | 12.4 | Accept |
C | 1,250,000 | 13.40% | 12.4 | Accept |
D | 1,250,000 | 13.20% | 12.4 | Accept |
E | 700,000 | 12.90% | 12.4 | Accept |
F | 700,000 | 12.30% | 10.4 | Accept |
G | 1,000,000 | 12.20% | 10.4 | Accept |
Capital Budget | 6,850,000 |