eBook
Hampton Manufacturing estimates that its WACC is 12.4%. The
company is considering the following seven investment projects:
Project |
Size |
IRR |
|
A |
|
$ 700,000 |
|
14.5 |
% |
B |
|
1,250,000 |
|
14.0 |
|
C |
|
1,250,000 |
|
13.4 |
|
D |
|
1,250,000 |
|
13.2 |
|
E |
|
700,000 |
|
12.9 |
|
F |
|
700,000 |
|
12.3 |
|
G |
|
1,000,000 |
|
12.2 |
|
- Assume that each of these projects is independent and that each
is just as risky as the firm's existing assets. Which set of
projects should be accepted?
Project A |
-Select-acceptdon't acceptItem 1 |
Project B |
-Select-acceptdon't acceptItem 2 |
Project C |
-Select-acceptdon't acceptItem 3 |
Project D |
-Select-acceptdon't acceptItem 4 |
Project E |
-Select-acceptdon't acceptItem 5 |
Project F |
-Select-acceptdon't acceptItem 6 |
Project G |
-Select-acceptdon't acceptItem 7 |
What is the firm's optimal capital budget? Write out your answer
completely. For example, 13 million should be entered as
13,000,000. Round your answer to the nearest dollar.
$
- Now, assume that Projects C and D are mutually exclusive.
Project D has an NPV of $450,000, whereas Project C has an NPV of
$400,000. Which set of projects should be accepted?
Project A |
-Select-acceptdon't acceptItem 9 |
Project B |
-Select-acceptdon't acceptItem 10 |
Project C |
-Select-acceptdon't acceptItem 11 |
Project D |
-Select-acceptdon't acceptItem 12 |
Project E |
-Select-acceptdon't acceptItem 13 |
Project F |
-Select-acceptdon't acceptItem 14 |
Project G |
-Select-acceptdon't acceptItem 15 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000. Round your answer to the nearest
dollar.
$
- Ignore previous part, and now assume that each of the projects
is independent but that management decides to incorporate project
risk differentials. Management judges Projects B, C, D, and E to
have average risk, Project A to have high risk, and Projects F and
G to have low risk. The company adds 2% to the WACC of those
projects that are significantly more risky than average, and it
subtracts 2% from the WACC for those that are substantially less
risky than average. Which set of projects should be accepted?
Project A |
-Select-acceptdon't acceptItem 17 |
Project B |
-Select-acceptdon't acceptItem 18 |
Project C |
-Select-acceptdon't acceptItem 19 |
Project D |
-Select-acceptdon't acceptItem 20 |
Project E |
-Select-acceptdon't acceptItem 21 |
Project F |
-Select-acceptdon't acceptItem 22 |
Project G |
-Select-acceptdon't acceptItem 23 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000. Round your answer to the nearest
dollar.
$
|