In: Finance
9. Problem 12.17 (Optimal Capital Budget)
| eBook
Hampton Manufacturing estimates that its WACC is 12.8%. The company is considering the following seven investment projects:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Project | Size | IRR | ||
| A | 650,000 | 14.50% | ||
| B | 1,150,000 | 14.00% | ||
| C | 1,150,000 | 13.70% | ||
| D | 1,250,000 | 13.50% | ||
| E | 800,000 | 13.20% | ||
| F | 800,000 | 12.60% | ||
| G | 750,000 | 12.30% | ||
| The projects whose return i.e. IRR is greater than the cost of capital should be accepted | ||||
| Project | Decision | |||
| A | Accept | |||
| B | Accept | |||
| C | Accept | |||
| D | Accept | |||
| E | Accept | |||
| F | Reject | |||
| G | Reject | |||
| Optimal Capital Budget | 5,000,000 | |||
| b.The project with higher NPV should be selected | ||||
| Project | Decision | |||
| A | Accept | |||
| B | Accept | |||
| C | Accept | |||
| D | Reject | |||
| E | Accept | |||
| F | Reject | |||
| G | Reject | |||
| Optimal Capital Budget | 3,750,000 | |||
| c. | ||||
| Project | Size | IRR | Required return | Decision |
| A | 650,000 | 14.50% | 14.8 | Reject |
| B | 1,150,000 | 14.00% | 12.8 | Accept |
| C | 1,150,000 | 13.70% | 12.8 | Accept |
| D | 1,250,000 | 13.50% | 12.8 | Accept |
| E | 800,000 | 13.20% | 12.8 | Accept |
| F | 800,000 | 12.60% | 10.8 | Accept |
| G | 750,000 | 12.30% | 10.8 | Accept |
| Capital Budget | 5,900,000 |