In: Finance
OPTIMAL CAPITAL BUDGET
Hampton Manufacturing estimates that its WACC is 12.5%. The company is considering the following seven investment projects:
Project | Size | IRR |
A | $750,000 | 14.0% |
B | 1,250,000 | 13.5 |
C | 1,250,000 | 13.2 |
D | 1,250,000 | 13.0 |
E | 750,000 | 12.7 |
F | 750,000 | 12.3 |
G | 750,000 | 12.2 |
Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted?
Project A | -Select-AcceptDon't acceptItem 1 |
Project B | -Select-AcceptDon't acceptItem 2 |
Project C | -Select-AcceptDon't acceptItem 3 |
Project D | -Select-AcceptDon't acceptItem 4 |
Project E | -Select-AcceptDon't acceptItem 5 |
Project F | -Select-AcceptDon't acceptItem 6 |
Project G | -Select-AcceptDon't acceptItem 7 |
What is the firm's optimal capital budget? Write out your answer
completely. For example, 13 million should be entered as
13,000,000.
$
Now assume that Projects C and D are mutually exclusive. Project D has an NPV of $400,000, whereas Project C has an NPV of $350,000. Which set of projects should be accepted?
Project A | -Select-AcceptDon't acceptItem 9 |
Project B | -Select-AcceptDon't acceptItem 10 |
Project C | -Select-AcceptDon't acceptItem 11 |
Project D | -Select-AcceptDon't acceptItem 12 |
Project E | -Select-AcceptDon't acceptItem 13 |
Project F | -Select-AcceptDon't acceptItem 14 |
Project G | -Select-AcceptDon't acceptItem 15 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000.
$
Ignore Part b and now assume that each of the projects is independent but that management decides to incorporate project risk differentials. Management judges Projects B, C, D, and E to have average risk, Project A to have high risk, and Projects F and G to have low risk. The company adds 2% to the WACC of those projects that are significantly more risky than average, and it subtracts 2% from the WACC of those projects that are substantially less risky than average. Which set of projects should be accepted?
Project A | -Select-AcceptDon't acceptItem 17 |
Project B | -Select-AcceptDon't acceptItem 18 |
Project C | -Select-AcceptDon't acceptItem 19 |
Project D | -Select-AcceptDon't acceptItem 20 |
Project E | -Select-AcceptDon't acceptItem 21 |
Project F | -Select-AcceptDon't acceptItem 22 |
Project G | -Select-AcceptDon't acceptItem 23 |
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000.
$