In: Finance
OPTIMAL CAPITAL BUDGET
Hampton Manufacturing estimates that its WACC is 12.5%. The company is considering the following seven investment projects:
| Project | Size | IRR | 
| A | $750,000 | 14.0% | 
| B | 1,250,000 | 13.5 | 
| C | 1,250,000 | 13.2 | 
| D | 1,250,000 | 13.0 | 
| E | 750,000 | 12.7 | 
| F | 750,000 | 12.3 | 
| G | 750,000 | 12.2 | 
Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted?
| Project A | -Select-AcceptDon't acceptItem 1 | 
| Project B | -Select-AcceptDon't acceptItem 2 | 
| Project C | -Select-AcceptDon't acceptItem 3 | 
| Project D | -Select-AcceptDon't acceptItem 4 | 
| Project E | -Select-AcceptDon't acceptItem 5 | 
| Project F | -Select-AcceptDon't acceptItem 6 | 
| Project G | -Select-AcceptDon't acceptItem 7 | 
What is the firm's optimal capital budget? Write out your answer
completely. For example, 13 million should be entered as
13,000,000.
$
Now assume that Projects C and D are mutually exclusive. Project D has an NPV of $400,000, whereas Project C has an NPV of $350,000. Which set of projects should be accepted?
| Project A | -Select-AcceptDon't acceptItem 9 | 
| Project B | -Select-AcceptDon't acceptItem 10 | 
| Project C | -Select-AcceptDon't acceptItem 11 | 
| Project D | -Select-AcceptDon't acceptItem 12 | 
| Project E | -Select-AcceptDon't acceptItem 13 | 
| Project F | -Select-AcceptDon't acceptItem 14 | 
| Project G | -Select-AcceptDon't acceptItem 15 | 
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000.
$
Ignore Part b and now assume that each of the projects is independent but that management decides to incorporate project risk differentials. Management judges Projects B, C, D, and E to have average risk, Project A to have high risk, and Projects F and G to have low risk. The company adds 2% to the WACC of those projects that are significantly more risky than average, and it subtracts 2% from the WACC of those projects that are substantially less risky than average. Which set of projects should be accepted?
| Project A | -Select-AcceptDon't acceptItem 17 | 
| Project B | -Select-AcceptDon't acceptItem 18 | 
| Project C | -Select-AcceptDon't acceptItem 19 | 
| Project D | -Select-AcceptDon't acceptItem 20 | 
| Project E | -Select-AcceptDon't acceptItem 21 | 
| Project F | -Select-AcceptDon't acceptItem 22 | 
| Project G | -Select-AcceptDon't acceptItem 23 | 
What is the firm's optimal capital budget in this case? Write
out your answer completely. For example, 13 million should be
entered as 13,000,000.
$