In: Finance
PROJECT SELECTION
Midwest Water Works estimates that its WACC is 10.59%. The company is considering the following capital budgeting projects.
Assume that each of these projects is just as risky as the firm's existing assets and that the firm may accept all the projects or only some of them. Which set of projects should be accepted?
Project | Size | Rate of Return | ||
A | $1 million | 12.0% | -Select-AcceptDon't acceptItem 1 | |
B | 2 million | 11.5 | -Select-AcceptDon't acceptItem 2 | |
C | 2 million | 11.2 | -Select-AcceptDon't acceptItem 3 | |
D | 2 million | 11.0 | -Select-AcceptDon't acceptItem 4 | |
E | 1 million | 10.7 | -Select-AcceptDon't acceptItem 5 | |
F | 1 million | 10.3 | -Select-AcceptDon't acceptItem 6 | |
G | 1 million | 10.2 | -Select-AcceptDon't accept Item 7 |
Since the Midwest Water Works estimates that its WACC is 10.59%?, it can accept all those projects with return of more than this WACC of 10.59%. So Midwest Water Works can accept all projects specified under, if it has no restriction on raising fund of $7million with this WACC of 10.59%.
Project | Size | Rate of Return | ||
A | $1 million | 12.0% | -Select-AcceptDon't acceptItem 1 | |
B | 2 million | 11.5 | -Select-AcceptDon't acceptItem 2 | |
C | 2 million | 11.2 | -Select-AcceptDon't acceptItem 3 | |
D | 2 million | 11.0 | -Select-AcceptDon't acceptItem 4 |
If the WACC goes more than 11%, it cannot accept project D, goes more than 11.2%, projects D &C, goes more than 11.5%, projects B, D &C, because the WACC or cost of overall fund does not exceed the rate of return.
Please rate the answer maximum if you get the answer and
satisfied. If you remains any doubts on this answer, please leave a
comment and it will be cleared.
Thank you,….