In: Accounting
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts.)
Thank you for your patience. Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Sarasota, Inc. | Calculation of Gross Profit | |
Particulars | 2020 | |
Contract Price | 6,504,000 | A |
Cost Incurred during the year | 1,639,900 | B |
Estimated cost to complete | 3,650,100 | C |
Cost Incurred to date | 1,639,900 | D |
(Sum total of the cost incurred during the year) | ||
Estimated total cost | 5,290,000 | E=C+D |
Percentage complete | 31.00% | F=D/E |
(Cost Incurred to date/Estimated total cost) | ||
Revenue to be recognized | 2,016,240 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||
Year 2020: 31% completed. Revenue recognized = 31% x $ 6,504,000 = $ 2,016,240. | ||
Gross Profit/(Loss) | 376,340.00 | H=G-B |
Billings during the year | 1,300,000.00 | |
Collection during the year | 1,055,000.00 |
Ans to 2 | Journal Entries | 2020 |
Costs Incurred | CIP (Work-in-progress) Dr. | 1,639,900 |
Cash Cr. | 1,639,900 | |
Billing | Accounts Receivable Dr. | 1,300,000 |
Billing on CIP Cr. | 1,300,000 | |
Receiving Payments | Cash Dr. | 1,055,000 |
Accounts Receivable Cr. | 1,055,000 | |
Period end adjustments for Revenue | Construction Expense Dr. | 1,639,900 |
CIP (Work-in-progress) Dr. | 376,340 | |
Construction Revenue Cr. | 2,016,240 |