In: Accounting
Problem 3
An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s):
20x0 20x1 20x2 20x3
Costs incurred during the year $ 6500 19500 25000 5800
Estimated costs to complete 38500 26000 6500 -
Billings 18000 18000 - 18000
For each of the parts below, prepare the ‘mini’ income statement for the project for each year and calculate the net investment of the project that will be shown on the balance sheet at the end of each year.
a. The entity uses an input based approach to calculating the percentage of completion.
b. The entity uses an output based approach to calculating the percentage of completion and has calculated the percentages of completion as follows: 20x0:16% | 20x1: 60% | 20x2: 90% | 20x3: 100%
A) | |||||
Percentage completion method | 2010 | 2011 | 2012 | 2013 | |
Cost incurred in till previous year | 0 | 6500 | 26000 | 51000 | |
ADD | Cost incurred during the year | 6500 | 19500 | 25000 | 5800 |
Total cost incurred till date | 6500 | 26000 | 51000 | 56800 | |
ADD | Estimated cost to be incurred | 38500 | 26000 | 6500 | 0 |
Total estimated cost to be incurred | 45000 | 52000 | 57500 | 56800 | |
Percentage of completion (A) | 14% | 50.00% | 89% | 100% | |
(cost incurred till date /total estimated cost ) | |||||
Total revenue (B) | 54000 | 54000 | 54000 | 54000 | |
Total revenue recognized (A *B) | 7800 | 27000 | 47896 | 54000 | |
Less | Revenue recognized in previous year | 0 | 7800 | 27000 | 47896 |
revenue recognized in current year | 7800 | 19200 | 20896 | 6104 | |
2010 | 2011 | 2012 | 2013 | ||
Revenue | 7800 | 19200 | 20896 | 6104 | |
Less | Cost incurred | 6500 | 19500 | 25000 | 5800 |
Gross profit | 1300 | -300 | -4104 | 304 | |
b) | |||||
Percentage completion method | 2010 | 2011 | 2012 | 2013 | |
Cost incurred in till previous year | 0 | 6500 | 26000 | 51000 | |
ADD | Cost incurred during the year | 6500 | 19500 | 25000 | 5800 |
Total cost incurred till date | 6500 | 26000 | 51000 | 56800 | |
ADD | Estimated cost to be incurred | 38500 | 26000 | 6500 | 0 |
Total estimated cost to be incurred | 45000 | 52000 | 57500 | 56800 | |
Percentage of completion (A) | 16% | 60.00% | 90% | 100% | |
(cost incurred till date /total estimated cost ) | |||||
Total revenue (B) | 54000 | 54000 | 54000 | 54000 | |
Total revenue recognized (A *B) | 8640 | 32400 | 48600 | 54000 | |
Less | Revenue recognized in previous year | 0 | 8640 | 32400 | 48600 |
revenue recognized in current year | 8640 | 23760 | 16200 | 5400 | |
2010 | 2011 | 2012 | 2013 | ||
Revenue | 8640 | 23760 | 16200 | 5400 | |
Less | Cost incurred | 6500 | 19500 | 25000 | 5800 |
Gross profit | 2140 | 4260 | -8800 | -400 | |