Question

In: Accounting

Problem 3 An entity entered into a construction contract to build a condo building at a...

Problem 3

An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s):

20x0 20x1 20x2 20x3

Costs incurred during the year $ 6500 19500 25000 5800

Estimated costs to complete 38500 26000 6500 -

Billings 18000 18000 - 18000

For each of the parts below, prepare the ‘mini’ income statement for the project for each year and calculate the net investment of the project that will be shown on the balance sheet at the end of each year.

a. The entity uses an input based approach to calculating the percentage of completion.

b. The entity uses an output based approach to calculating the percentage of completion and has calculated the percentages of completion as follows: 20x0:16% | 20x1: 60% | 20x2: 90% | 20x3: 100%

Solutions

Expert Solution

A)
Percentage completion method 2010 2011 2012 2013
Cost incurred in till previous year 0 6500 26000 51000
ADD Cost incurred during the year 6500 19500 25000 5800
Total cost incurred till date 6500 26000 51000 56800
ADD Estimated cost to be incurred 38500 26000 6500 0
Total estimated cost to be incurred 45000 52000 57500 56800
Percentage of completion (A) 14% 50.00% 89% 100%
(cost incurred till date /total estimated cost )
Total revenue (B) 54000 54000 54000 54000
Total revenue recognized (A *B) 7800 27000 47896 54000
Less Revenue recognized in previous year 0 7800 27000 47896
revenue recognized in current year 7800 19200 20896 6104
2010 2011 2012 2013
Revenue 7800 19200 20896 6104
Less Cost incurred 6500 19500 25000 5800
Gross profit 1300 -300 -4104 304
b)
Percentage completion method 2010 2011 2012 2013
Cost incurred in till previous year 0 6500 26000 51000
ADD Cost incurred during the year 6500 19500 25000 5800
Total cost incurred till date 6500 26000 51000 56800
ADD Estimated cost to be incurred 38500 26000 6500 0
Total estimated cost to be incurred 45000 52000 57500 56800
Percentage of completion (A) 16% 60.00% 90% 100%
(cost incurred till date /total estimated cost )
Total revenue (B) 54000 54000 54000 54000
Total revenue recognized (A *B) 8640 32400 48600 54000
Less Revenue recognized in previous year 0 8640 32400 48600
revenue recognized in current year 8640 23760 16200 5400
2010 2011 2012 2013
Revenue 8640 23760 16200 5400
Less Cost incurred 6500 19500 25000 5800
Gross profit 2140 4260 -8800 -400

Related Solutions

Raider Red Construction entered into a contract to build a commercial building for $3,600,000. Raider Red...
Raider Red Construction entered into a contract to build a commercial building for $3,600,000. Raider Red Construction uses the percentage-of-completion method for recognizing revenue on the project. Construction began in September of 2018 and the building was completed in June of 2020. The company provided the following additional information on the project. 2018 2019 2020 Costs incurred to date $                 725,000 $              2,100,000 $              3,400,000 Estimated costs to complete $              2,175,000 $              1,400,000 $                             -   Billings during the year $                ...
A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000. Construction commenced on 1 January 2021. The following details relate to the construction project as at 31 December 2021:                                                   S'000Progress billing to-date             5,520Cash receipt to-date                  5,120Costs incurred to-date               4,032Estimated total costs                  6,400Stone Age Construction Pte Ltd accounted for the contract using the percentage-of-completion method.Required:(a) For the year ended 2021, calculate the percentage of completion to-date, revenue recognised for the year...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build...
Problem #2 Pedroni Construction Company has entered into a contract beginning January 1, 2107, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017                2018                2019 Costs to date                                    $270,000          $450,000          $610,000 Estimated costs to complete             330,000             150,000               0 Progress billing to date                       270,000             550,000            900,000 Cash...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018   Costs incurred during the year $ 50 Estimated costs to complete as of December 31 $200 2019  Costs incurred during...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT