In: Accounting
Ipswich Construction Company is a private company that follows ASPE. The company has a December 31 year-end. Ipswich commenced business operations on January 1, 2020. The company’s board of directors is currently meeting to choose between use of the completed-contract method and use of the percentage-of-completion method for reporting long-term construction contracts in its financial statements. You have been engaged to assist the company’s controller at the board meeting and have been provided with the following information:
construction activities for the year ended december 31, 2020
Total Contract Billings Through Cash Collections
Project Price 12/31/20 Through 12/31/20
A $ 615,000 $ 340,000 $ 310,000
B 450,000 135,000 135,000
C 475,000 475,000 390,000
D 600,000 240,000 160,000
E 480,000 400,000 400,000
$2,620,000 $1,590,000 $1,395,000
Contract Costs Estimated
Incurred Through Additional Costs to
Project 12/31/20 Complete Contract
A $ 510,000 $120,000
B 130,000 260,000
C 350,000 -0-
D 370,000 290,000
E 320,000 80,000
$1,680,000 $750,000
Each contract is with a different customer and any work remaining to be done on contracts is expected to be completed in 2021.
Required:
Note: Supporting calculations must be shown.
Ans : PLEASE GV A RATING IF U LIKE MY EFFORTS , IT WILL KEEP US MOTIVATED. THANK YOU In Advance
Percentage of Completion
The percentage of completion method allows for the recognition of revenues, expenses, and taxes during the period that a contract is being executed. Through frequent reporting, percentage reporting reduces the risk of fluctuations while affording tax deferral benefits.
The percentage of completion method must be used if the revenues and costs of a project can be reasonably estimated and the parties involved are expected to be able to complete all duties.
Completed Contract
The completed contract method (CCM) of accounting considers all income and expenses directly related to a long-term contract as received when work is completed. The date of completion is spelled out in the contract and is often months or even years away from the date work begins.
Though a construction company may enjoy a break from taxes during the working phase—and sometimes may even qualify for certain tax incentives in the meantime—this method can be a riskier way to account for operations.
Note 1 : Completed contract method
Projects |
A |
B |
C |
D |
E |
Contract price (1) |
615,000 |
450,000 |
475,000 |
600,000 |
480,000 |
Contract costs incurred |
510,000 |
130,000 |
350,000 |
370,000 |
320,000 |
Additional Costs to complete |
120,000 |
260,000 |
0 |
290,000 |
80,000 |
Total cost (2) |
6,30,000 |
3,90,000 |
3,50,000 |
6,60,000 |
4,00,000 |
Total gross profit or (loss) (1-2) |
(15,000) |
60,000 |
1,25,000 |
(60,000) |
80,000 |
a) The amount reported as income (loss) under the completed-contract method for 2020 is:
Project A |
(15,000) |
Project B |
0 ( Since anticipated Profit is not booked ) |
Project C |
125,000 ( This is already complete , since additional cost is ‘ 0 ‘ ) |
Project D |
(11,000) |
Project E |
0 ( Since anticipated Profit is not booked ) |
Total |
99000 |
b) The amount reported as income (loss) under the percentage-of-completion for 2020 is:
Project A |
(15,000) |
Project B |
20000 [ (60,000 * 130,000 ) / 3,90,000 ] |
Project C |
125,000 ( This is already complete , since additional cost is ‘ 0 ‘ ) |
Project D |
(11,000) |
Project E |
64000 [ (80,000 * 320,000 ) / 400000 ] |
Total |
183000 |
Formula in case of profit = (gross profit * cost incurred in 2020 ) / Total Estimated cost
c)
Accounts title and Explanation |
Debit ($) |
Credit ($) |
Construction in Process |
20000 |
|
Construction Expenses |
130,000 |
|
Revenue from Long-term Contracts |
150,000 |