Question

In: Accounting

Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:...

Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:

Setting up equipment $598,000
Other overheard $6,400,000

Setting up equipment is based on setup hours, and other overhead is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on each product is as follows:

Fudge Cookies
Units produced 8,000 445,000
Setup hours 10,400 2,600
Oven hours 5,000 35,000

Required:

Round your answers to the nearest whole dollar, unless otherwise directed.

1. Calculate the activity rate for (a) setting up equipment and (b) other overhead.

a. Setting up equipment $ per setup hour
b. Other overhead $ per oven hour

2. How much total overhead is assigned to Fudge using ABC?
$

3. What is the unit overhead assigned to Fudge using ABC? Round to the nearest cent.
$per unit

4. Now, ignoring the ABC results, calculate the plantwide overhead rate, based on oven hours.
$ per oven hour

5. How much total overhead is assigned to Fudge using the plantwide overhead rate?
$

6a. The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because .

6b. What is the difference in total overhead assigned to fudge under the two methods?

$

Solutions

Expert Solution

1)
Setting up equipment (598,000/13,000)= 46 per setup hour
Other overhead (6,400,000/40,000)= 160 per oven hour
2) total overhead assigned to Fudge
Setting up Equipment (46*10,400) 478400
other overhead (160*5000)= 800000
total overhead assigned to Fudge 1278400
3) unit overhead assigned to Fudge
1,278,400/8,000
159.8
4) plantwide overhead rate
(598000+6,400,000)/40,000
174.95
5) overhead assigned to Fudget
174.95*5000
874750
6a) difference is due to different treatment of setup costs as under traditional method
oven hours is used whereas under ABC setup hours is used to assign cost
because of which overhead assigned is more under ABC as Fudge consumes more of
set up hours
6b) difference
1,278,400 - 874,750
403650 answer

Related Solutions

Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overheard $2,304,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $322,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $5,208,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 4,200 29,400 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $720,000 Other overheard $2,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $870,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $230,000 Other overheard $1,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,000 7,000 Required: Round your answers to the...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table below. In addition, they have two product lines, A100 and B100. Activity Cost Cost Driver A100 B100 Cost allocation base Setup $85,600 # of setups 1,600 1,750 16,000 Handling $136,500 # of parts 1,480 360 65,000 Assembly $126,000 Direct Labor Hours 800 365 5,000 Total $348,100 Summary of prime costs: A100 B100 Direct materials $16,000 $9,500 Direct labor $13,400 $12,700 Calculate the unit cost...
Company uses activity-based costing to determine product cost. The accounting department identified the following overhead activities,...
Company uses activity-based costing to determine product cost. The accounting department identified the following overhead activities, costs, and activity drivers for the coming year. Activity Estimated cost Activity driver Activity capacity Setting up equipment $120,000 Number of setups 300 Ordering materials 90,000 Number of orders 9,000 Maintaining machines 210,000 Machine hours 21,000 Total overhead $420,000 The following actual results were collected for the production of Model X and Model Y during the year. Model X Model Y Units produced 8,000...
5)X Company uses an activity-based costing overhead allocation system. It has identified three activities - Material...
5)X Company uses an activity-based costing overhead allocation system. It has identified three activities - Material handling, Product testing, Packaging - and their respective cost drivers - pounds of material, tests, packages. Budgeted activity costs in 2018 were as follows: Activity Budgeted Cost   Material handling $104,700       Product testing 58,700       Packaging 53,000       The following 2018 cost driver information is available for one of its products, Product A, and for all of its products (including Product A): Product A All Products pounds...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT