In: Accounting
Comparing ABC and Plantwide Overhead Cost Assignments
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:
| Setting up equipment | $870,000 | 
| Other overheard | $5,800,000 | 
Setting up equipment is based on setup hours, and other overhead
is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on
each product is as follows:
| Fudge | Cookies | ||||
| Units produced | 8,000 | 445,000 | |||
| Setup hours | 12,000 | 3,000 | |||
| Oven hours | 5,000 | 35,000 | |||
Required:
Round your answers to the nearest whole dollar, unless otherwise directed.
1. Calculate the activity rate for (a) setting up equipment and (b) other overhead.
| a. Setting up equipment | $ per setup hour | 
| b. Other overhead | $ per oven hour | 
2. How much total overhead is assigned to Fudge
using ABC?
$
3. What is the unit overhead assigned to Fudge
using ABC? Round to the nearest cent.
$per unit
4. Now, ignoring the ABC results, calculate the
plantwide overhead rate, based on oven hours.
$ per oven hour
5. How much total overhead is assigned to Fudge
using the plantwide overhead rate?
$
6a. The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because .
6b. What is the difference in total overhead assigned to fudge under the two methods?
| 1 | A | Activity | B | A/B | ||||
| Activity Pool | Costs | Fudge | Cookies | Total Activity | Activity Rate | |||
| Setting Up Equipment | 870000 | 12000 | 3000 | 15000 | 58.00 | |||
| Other Overhead | 5800000 | 5000 | 35000 | 40000 | 145.00 | |||
| 6670000 | ||||||||
| Activity Pool | Activity Rate | |||||||
| Setting Up Equipment | 58.00 | Per Setup H | ||||||
| Other Overhead | 145.00 | Per Oven H | ||||||
| 2&3 | Assigned to Fudge: | A | B | A*B | ||||
| Activity Pool | Activity in Fudge | Activity Rate | Assignment | |||||
| Setting Up Equipment | 12000 | 58 | 696000 | |||||
| Other Overhead | 5000 | 145 | 725000 | |||||
| 1421000 | ||||||||
| Total | 8000 | |||||||
| PU Cost | 177.625 | |||||||
| 4 | Total Overhead | 6670000 | ||||||
| Total Oven Hours | 40000 | |||||||
| Overhead per Oven Hours | 166.75 | |||||||
| 5 | Oven Hours in Fudge | 5000 | ||||||
| Overhead per Oven Hours | 166.75 | |||||||
| Assigned OH to Fudge | 833750 | |||||||
| 6A | The Difference is because of Assigned in ABC was more accurate and Less Accurate in Traditional Costing | |||||||
| 6B | ABC Method | 1421000 | ||||||
| Traditional Costing | 833750 | |||||||
| Difference | 587250 | |||||||