Question

In: Accounting

Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...

Comparing ABC and Plantwide Overhead Cost Assignments

Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:

Setting up equipment $720,000
Other overheard $2,160,000

Setting up equipment is based on setup hours, and other overhead is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on each product is as follows:

Fudge Cookies
Units produced 8,000 445,000
Setup hours 12,000 3,000
Oven hours 1,800 12,600

Required:

Round your answers to the nearest whole dollar, unless otherwise directed.

1. Calculate the activity rate for (a) setting up equipment and (b) other overhead.

a. Setting up equipment $ per setup hour
b. Other overhead $ per oven hour

2. How much total overhead is assigned to Fudge using ABC?
$

3. What is the unit overhead assigned to Fudge using ABC? Round to the nearest cent.
$per unit

4. Now, ignoring the ABC results, calculate the plantwide overhead rate, based on oven hours.
$ per oven hour

5. How much total overhead is assigned to Fudge using the plantwide overhead rate?
$

6a. The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because  .

6b. What is the difference in total overhead assigned to fudge under the two methods?

$

Solutions

Expert Solution

1) Calculation of Activity Rate (Amounts in $)

Setting up equipment Other overhead
Total Estimated overheads (A) 720,000 2,160,000
Activity Base Setup hours Oven hours
Total Activity base hours (B) 15,000 (12,000+3,000) 14,400 (1,800+12,600)
Activity Rate (A/B) $48 per setup hour $150 per oven hour

Therefore the activity rate is:-

a. Setting up equipment $48 per setup hour
b. Other overhead $150 per oven hour

2) Calculation of total overhead assigned to Fudge using ABC (Amounts in $)

Allocated setting up equipment ($48*12,000 setup hours) (a) 576,000
Allocated other overhead ($150*$1,800 oven hours) (b) 270,000
Total Allocated Overhead to Fudge (a+b) 846,000

3) Unit Overhead assigned to Fudge = Total Assigned Overhead/Units produced

= $846,000/8,000 = $105.75 per unit

Therefore unit overhead assigned to Fudge using ABC is $105.75 per unit.

4) Plantwide Overhead rate = Total Budgeted Overhead/Total Oven hours

Total Budgeted Overheads = Setting up Equipment+Other Overheads

= $720,000+$2,160,000 = $2,880,000

Total Oven hours = 1,800+12,600 = 14,400 hours

Plantwide Overhead rate = = $2,880,000/14,400 hrs = $200 per oven hour

Therefore the plantwide overhead rate, based on oven hours is $200 per oven hour.

5) Total overhead assigned to Fudge using plantwide rate = Plantwide OH rate*Oven hours

= $200 per oven hour*1,800 hrs = $360,000

6a) The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because plantwide overhead rate is used for allocating overhead which is based only on Oven hours whereas under ABC system, different activity rates based on setup hours and oven hours are used to allocate setting up and other overhead cost separately.

6b) Diff in Overhead assigned under two methods = $846,000 - $360,000 = $486,000


Related Solutions

Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overheard $2,304,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $322,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $5,208,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 4,200 29,400 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $870,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $230,000 Other overheard $1,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,000 7,000 Required: Round your answers to the...
Wellington Chocolate Company uses activity-based costing. The controller identified two activities and budgeted overhead costs based...
Wellington Chocolate Company uses activity-based costing. The controller identified two activities and budgeted overhead costs based on these activities: Setting up equipment $280,000 Baking $5,800,000 Setting up equipment is based on setup hours, and baking is based on oven hours. Wellington produces two products, fudge, and cookies. Information on each product is as follows fudge cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 5,000 35,000 Required (round your answers to the nearest whole dollar, unless otherwise directed):...
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:...
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $598,000 Other overheard $6,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 10,400 2,600 Oven hours 5,000 35,000 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1....
ABC is a job-order costing manufacturer that uses a plantwide overhead rate based on machine hours....
ABC is a job-order costing manufacturer that uses a plantwide overhead rate based on machine hours. Estimations for the year include $2,000,000 in overhead and 1,000,000 machine hours. ABC produced four products in March. Data are as follows: Product89 Product90 Product91 Product92 Balance, 3/1 $70,000     $20,000       $         0 $         0 Direct materials $30,000 $80,000 $100,000 15,000 Direct labor cost $25,000 $ 40,000 $60,000 $10,000 Actual machine hours – for month   1,000   2,000 3,000   500 By March 31, Jobs 89,...
Implementation of Activity-based costing (ABC) The case of a Juice Company John Orland, controller of the...
Implementation of Activity-based costing (ABC) The case of a Juice Company John Orland, controller of the Juice Company, has been concerned over the erosion of the recent financial results especially for the standard flavors (A and B) which used to earn a hefty 20 per cent of profit margin. Recently, Dan Brun, the sales manager has expanded the lines of products to encompass new flavors (B & C) which were in high demand by customers who were willing to pay...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. ? Activity Cost Driver Amount of driver setups $240,000 number of setups 6,000 purchasing 160,000 number of parts 20,000 other overhead 300,000 direct labor hours 80,000 ? The following information about the jobs was given for April. ? ? Job 101 Job 102 Job 103 Job 104 Balance 4/1 $64,900 $40,770 $30,500 0 direct...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT