In: Accounting
Comparing ABC and Plantwide Overhead Cost Assignments
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:
Setting up equipment | $270,000 |
Other overheard | $2,160,000 |
Setting up equipment is based on setup hours, and other overhead
is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on
each product is as follows:
Fudge | Cookies | ||||
Units produced | 8,000 | 445,000 | |||
Setup hours | 4,000 | 1,000 | |||
Oven hours | 1,800 | 12,600 |
Required:
Round your answers to the nearest whole dollar, unless otherwise directed.
1. Calculate the activity rate for (a) setting up equipment and (b) other overhead.
a. Setting up equipment | $ per setup hour |
b. Other overhead | $ per oven hour |
2. How much total overhead is assigned to Fudge
using ABC?
$
3. What is the unit overhead assigned to Fudge
using ABC? Round to the nearest cent.
$per unit
4. Now, ignoring the ABC results, calculate the
plantwide overhead rate, based on oven hours. Round to the nearest
cent.
$ per oven hour
5. How much total overhead is assigned to Fudge
using the plantwide overhead rate?
$
6a. The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because .
6b. What is the difference in total overhead assigned to fudge under the two methods?
$
Ans.No | Particulars | Amount $ | Remarks | |
1 | Setting up equipment | $ 54.00 | $ per setup hour | (270,000/5000) |
Other overhead | $ 150.00 | $ per oven hour | (2,160,000/(1800+12,600)) | |
2 | total overhead is assigned to Fudge using ABC | $ | ||
Setting up equipment | $ 216,000.00 | (54*4,000) | ||
Other overhead | $ 270,000.00 | (150*1,800) | ||
total overhead is assigned to Fudge using ABC | $ 486,000.00 | |||
3 | unit overhead assigned to Fudge using ABC | $ 60.75 | $per unit | (486,000/8,000) |
4 | plantwide overhead rate, based on oven hours | $ 168.75 | $ per oven hour | (270,000+2,160,000)/(18,00+12,600) |
5 | total overhead is assigned to Fudge using the plantwide overhead rate | $ 303,750.00 | (168.75*1,800) | |
6a | Because in abc cost allocation cost is allocated based on their respective setting up hour | |||
and oven hours where as in non abc cost is allocated on overall average of company. | ||||
As fudge has higher hours compared to other ,so hiher allocated in ABC System | ||||
6b | difference in total overhead assigned to fudge under the two methods | $ 182,250.00 | (486,000-303,750) | |