Question

In: Accounting

Production Inc. uses activity based costing. The following estimated activity costs are identified in the table...

Production Inc. uses activity based costing. The following estimated activity costs are identified in the table below. In addition, they have two product lines, A100 and B100.

Activity Cost Cost Driver A100 B100 Cost allocation base
Setup $85,600 # of setups 1,600 1,750 16,000
Handling $136,500 # of parts 1,480 360 65,000
Assembly $126,000 Direct Labor Hours 800 365 5,000
Total $348,100
Summary of prime costs: A100 B100
Direct materials $16,000 $9,500
Direct labor $13,400 $12,700


Calculate the unit cost for the two products, A100 and B100.
Do not enter dollar signs or commas in the input boxes.
Round Activity Rate to 2 decimal places. Round all other answers to the nearest whole number.

Activity Cost Cost allocation base Activity Rate
Setup $Answer Answer $Answer
Handling $Answer Answer $Answer
Assembly $Answer Answer $Answer
Total $Answer $Answer
A100 B100
Cost Type Activity amount Cost Amount Activity amount Cost Amount
Direct materials $Answer $Answer
Direct labor $Answer $Answer
Setup Answer $Answer Answer $Answer
Handling Answer $Answer Answer $Answer
Assembly Answer $Answer Answer $Answer
Total $Answer $Answer

Solutions

Expert Solution

Activity Cost Cost Driver A100 B100 Cost allocation base
Setup 85,600 # of setups 1,600 1,750 16,000
Handling 136,500 # of parts 1,480 360 65,000
Assembly 126,000 Direct Labor Hours 800 365 5,000
Total 348,100
Activity Cost Cost allocation base Acitivity Rate
Setup 85,600 16,000 5.35
Handling 136,500 65,000 2.10
Assembly 126,000 5,000 25.20
Total 348,100
A100 B100 Acitivity Rate
Activity Activity Amount Cost Amount Activity Amount Cost Amount
Direct Material                     16,000.0           9,500.0
Direct Labor                     13,400.0         12,700.0 5.35
Setup 1,600                       8,560.0 1,750           9,362.5 (Activity Rate* Activity Usage) 2.10
Handling 1,480                       3,108.0 360              756.0 25.20
Assembly 800                     20,160.0 365           9,198.0
Total                     61,228.0 41516.5

Related Solutions

Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:...
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $598,000 Other overheard $6,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 10,400 2,600 Oven hours 5,000 35,000 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1....
Part 3: Activity-Based Costing Banquet Services uses activity-based costing to compute the costs of their catered...
Part 3: Activity-Based Costing Banquet Services uses activity-based costing to compute the costs of their catered parties. Each party is limited to 40 guests and requires five people to serve and clean up. Two types of parties, an afternoon picnic and an evening formal dinner, are offered. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $175 per party $100 per party Planning (parties) $50 per party $75 per party Renting equipment $75...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires 5 people to serve and clean up. Cathy offers two types of parties, an afternoon picnic and an evening formal dinner. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 79 per party $ 79 per party Planning (parties) $ 72 per party $ 104...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires four people to serve and clean up. Cathy offers two types of parties, an afternoon picnic and an evening formal dinner. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 100 per party $ 100 per party Planning (parties) $ 75 per party $ 125...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires 4 people to serve and clean up. Cathy offers two types of parties, an afternoon picnic and an evening formal dinner. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 121 per party $ 121 per party Planning (parties) $ 52 per party $ 112...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires 5 people to serve and clean up. Cathy offers two types of parties, an afternoon picnic and an evening formal dinner. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 105 per party $ 105 per party Planning (parties) $ 64 per party $ 102...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires 4 people to serve and clean up. Cathy offers two types of parties—an afternoon picnic and an evening formal dinner. The breakdown of the costs follows. Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 97 per party $ 97 per party Planning (parties) $ 56 per party $ 140 per...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her...
Cathy, the manager of Cathy’s Catering, Inc., uses activity-based costing to compute the costs of her catered parties. Each party is limited to 20 guests and requires 4 people to serve and clean up. Cathy offers two types of parties, an afternoon picnic and an evening formal dinner. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $ 93 per party $ 93 per party Planning (parties) $ 50 per party $ 130...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT