In: Finance
Period Project A Project B Project C
T=0 ($3,000) ($5,000) ($2,000)
T=1 $1,000 $1,500 $900
T=2 $1,200 $1,500 $900
T=3 $1,500 $2,500 $700
T=4 $1,500 $2,500 $700
When you have only $5,000 to support the above projects, which project (or projects) should be chosen under the Profitability Index?