Question

In: Finance

Find out the NPV, IRR and Payback period for each of the following three projects. Assume...

  1. Find out the NPV, IRR and Payback period for each of the following three projects.

Assume I=6%.                       

                                                                                                            (60 points)

Project

CF0

CF1

CF2

CF3

CF4

CF5

A

-12,000

3000

3000

4000

4000

1000

B

-12,000

4000

4000

3000

3000

1000

C

-12,000

3000

3000

3000

3000

1000

D

-12,000

5000

3000

5000

3000

0

E

-12,000

3000

3000

3000

3000

5000

F

-12,000

0

0

6000

6000

6000

Solutions

Expert Solution

Using excel to calculate NPV

A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5 NPV Excel Formula
1 A -12,000 3000 3000 4000 4000 1000 774.29 NPV(6%,B1:F1)+A1
2 B -12,000 4000 4000 3000 3000 1000 975.97 NPV(6%,B2:F2)+A2
3 C -12,000 3000 3000 3000 3000 1000 -857.42 NPV(6%,B3:F3)+A3
4 D -12,000 5000 3000 5000 3000 0 1961.35 NPV(6%,B4:F4)+A4
5 E -12,000 3000 3000 3000 3000 5000 2131.61 NPV(6%,B5:F5)+A5
6 F -12,000 0 0 6000 6000 6000 2273.83 NPV(6%,B6:F6)+A6
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5 IRR Excel Formula
1 A -12,000 3000 3000 4000 4000 1000 8.49% IRR(A1:F1)
2 B -12,000 4000 4000 3000 3000 1000 9.48% IRR(A2:F2)
3 C -12,000 3000 3000 3000 3000 1000 3.05% IRR(A3:F3)
4 D -12,000 5000 3000 5000 3000 0 13.34% IRR(A4:F4)
5 E -12,000 3000 3000 3000 3000 5000 11.84% IRR(A5:F5)
6 F -12,000 0 0 6000 6000 6000 10.76% IRR(A6:F6)

Payback Period Using excel

A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 A -12,000 3000 3000 4000 4000 1000
2 Cumulative Cash Flow -12,000 -9,000 -6,000 -2,000 2,000 3,000
Payback Period 3.50 (3+2000/4000)
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 B -12,000 4000 4000 3000 3000 1000
2 Cumulative Cash Flow -12,000 -8,000 -4,000 -1,000 2,000 3,000
Payback Period 3.33 (3-1000/3000)
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 C -12,000 3000 3000 3000 3000 1000
2 Cumulative Cash Flow -12,000 -9,000 -6,000 -3,000 0 1,000
Payback Period 4.00 (4+0)
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 D -12,000 5000 3000 5000 3000 0
2 Cumulative Cash Flow -12,000 -7,000 -4,000 1,000 4,000 4,000
Payback Period 2.80 (=2+4000/5000)
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 E -12,000 3000 3000 3000 3000 5000
2 Cumulative Cash Flow -12,000 -9,000 -6,000 -3,000 0 5,000
Payback Period 4.00 4
A B C D E F
Project CF0 CF1 CF2 CF3 CF4 CF5
1 F -12,000 0 0 6000 6000 6000
2 Cumulative Cash Flow -12,000 -12,000 -12,000 -6,000 0 6,000
Payback Period 4.00 4

Please Discuss in case of Doubt

Best of Luck. God Bless
Please Rate Well


Related Solutions

Find out the NPV, IRR and Payback period for each of the following three projects. Assume...
Find out the NPV, IRR and Payback period for each of the following three projects. Assume I=6%. Please show work and write out answers. Do not put into a table. Thank you    Project CF0 CF1 CF2 CF3 CF4 CF5 A -12,000 3000 3000 4000 4000 1000 B -12,000 4000 4000 3000 3000 1000 C -12,000 3000 3000 3000 3000 1000 D -12,000 5000 3000 5000 3000 0 E -12,000 3000 3000 3000 3000 5000 F -12,000 0 0 6000...
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required...
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 12%. Cashflow for each year Project A : Year 0= -2500 Year 1=900 Yaer 2=800 Year 3=1600 Year 4=100 Yaer 5=50 Year 6= 300 Project B Year 0 =-2500 Year 1=50 Year2= 600 Year 3=150 Year 4=900 Year 5= 500 Year 6=2500
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each...
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years. Risk free rate = 1.10%, MRP = 9.5%, Required return = 14.40% Yes excel is fine Expected cash flows for the four potential projects that Avalon is...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?
Considering the following projects.ProjectYear01234ACash flows-$100$35$35$35$35BCash flows-$100$60$50$40$30Project A has WACC = 6.00% while project B has WACC = 8.50%.If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?Would your decision (Your answer from part A) change if these two projects were independent?
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of...
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of these projects. When would you choose one over the other (i.e. what is the crossover rate)? Draw the NPV profile using 11 intervals of interest rates ranging from (and including) 0% to 100%. Place all data, ratios, calculations, findings, etc. in the first Excel sheet with references to the information in other sheets. Time A CF B CF 0 -10000 -10000 1 12000 9000...
How does the NPV, IRR and the payback period of an Investment usually react to the...
How does the NPV, IRR and the payback period of an Investment usually react to the following developments (please indicate, UP/DOWN or N/A)? 1. Increasing Investment amount 2. Increasing tax rate 3. Increased annual depreciation due to change of depreciation method 4. Increasing cost of capital 5. Increasing residual value So I actually Need 15 indications (5*3) - TIA
You evaluate ALL of its projects by applying the Payback, Discounted Payback, NPV, and IRR rules....
You evaluate ALL of its projects by applying the Payback, Discounted Payback, NPV, and IRR rules. Assume the cost of capital is 10%. Assume cash flows of: TIME               CASH FLOWS -------------------------------------------------------------- 0               -$100 1               +$75 2               +$50 3               +$25 What is the payback?                                What is the Discounted Payback?                                What...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT