Question

In: Accounting

Edward Foster is a building contractor. He and his customer have agreed that he will submit...

Edward Foster is a building contractor. He and his customer have agreed that he will submit a bill to them when he is 25 percent complete, 50 percent complete, 75 percent complete, and 100 percent complete. For example, he has a $200,000 room addition. When he has completed 25 percent, he will bill his customer $50,000. The problem occurs when he is 40 percent complete, has incurred expenses but cannot yet bill his customer. How can his revenue and expenses match? Discuss several ways that Edward's accountant could solve this problem. What accounts would be used?

Solutions

Expert Solution

1) Percentage of Completion Method

The percentage of completion method for recognizing revenue is typically used in large or long-term projects. Firms that provide construction services, engineering services or other services with long projects are most likely to use this method. Providers of these services need to be able to demonstrate that they are generating revenue even though projects are not yet complete.

The percentage of completion method may only be used if both of the following requirements are met:

There is a long-term contract in place that is enforceable by law.
The project is set up in a way that allows for the percentage of completion to be estimated in order to allocate both revenue and expenses.

The percentage of completion method can be computed in two ways:

Revenue may be recognized at specific milestones. For a building, that could be a specific number of square feet, or a web design firm may have milestones of a specific number of pages for a website.
The percentage of completion may also be calculated based on cost. For example, if a firm expects costs to total $1,000,000 and they have incurred $300,000 in cost, the project would be seen as 30 percent complete.

While this revenue recognition method provides an alternative for long-term contracts, revenues may be overstated if the timing for expenses and completion of work are not properly aligned.

2) Completed Contract Method

When the completed contract method is used, revenue is recognized only once the project is complete and the contract is fulfilled. This method applies to both revenue and expenses. The only time this revenue recognition method is used is when the requirements of the percentage of completion method are unable to be met. For example, if a contract is not enforceable or if completion percentage cannot be calculated.

Since revenues are not recognized until a project is complete, the completed contract method runs the risk of under-reporting revenue at the time it is earned and overstating revenue once it is recognized.

3) Sales Basis Method

With the sales basis revenue recognition methods, revenue is recorded at the time of sale. Sale is defined as the period of time where goods and services change hands, which may or may not be at the same time as payment.

For example, if a customer makes payment before they receive delivery of the product, the revenue isn’t recognized until the product is delivered.

Thanks


Related Solutions

Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased...
Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased the tile and the contractor will be reimbursed for labor only. The contractor assumes he can complete one room per day at eight hours per day and at a cost of $1000/day or $1000 per room The planned cost is $40,000 and the planned duration is 40 days Current status At the end of 6 weeks (30 days). The contractor has completed 24 rooms...
The factory building manager at Delectable Delights, Jason Short, is concerned that the new contractor he...
The factory building manager at Delectable Delights, Jason Short, is concerned that the new contractor he hired is taking too long to replace defective lights in the factory workspace. He would like to perform a hypothesis test to determine if the replacement time for the lights under the new contractor is in fact longer than the replacement time under the previous contractor, which was 3.2 days on average. He selects a random sample of 12 service calls to replace defective...
Bob just had his annual physical and agreed with his doctor that he needs to lose...
Bob just had his annual physical and agreed with his doctor that he needs to lose weight and eat a healthier diet. On the way home, he stopped at the drive-through and got a double bacon cheeseburger and deep-fried cheese curds. Bob is experiencing cognitive dissonance, what can he do?
one of your customer is delinquent on his account payable balance youve mutually agreed to a...
one of your customer is delinquent on his account payable balance youve mutually agreed to a repayment of $550 per month
A building contractor buys 80% of his cement from supplier A and 20​% from supplier B....
A building contractor buys 80% of his cement from supplier A and 20​% from supplier B. A total of 75​% of the bags from A arrive​ undamaged, while 85​% of the bags from B arrive undamaged. Find the probability that a damaged bag is from supplier Upper A.
A building contractor buys 70​% of his cement from supplier A and 30​% from supplier B....
A building contractor buys 70​% of his cement from supplier A and 30​% from supplier B. A total of 95​% of the bags from A arrive​ undamaged, and a total of 90​% of the bags from B arrive undamaged. Find the probability that a damaged bag is from supplier Upper A.
Syd is an independent contractor driving for Uber. He currently uses his own car and drives...
Syd is an independent contractor driving for Uber. He currently uses his own car and drives whenever he chooses to supplement is full-time position as a factory assembly line worker. Please answer the following, briefly explaining your answers. Is Syd be properly classified as independent contractor for federal income tax purposes? Would the analysis be the same under the recent California supreme court (Dynamex) case? What key factor do these two tests have in common?
d) A building contractor calls the project office and asks if the necessary funds have been...
d) A building contractor calls the project office and asks if the necessary funds have been secured for construction work to begin. What document is required from the project company to the construction company for works to begin?
d) A building contractor calls the project office and asks if the necessary funds have been...
d) A building contractor calls the project office and asks if the necessary funds have been secured for construction work to begin. What document is required from the project company to the construction company for works to begin?
5.   Edward has diabetes mellitus type 2 (DM type 2).He is struggling to maintain his blood...
5.   Edward has diabetes mellitus type 2 (DM type 2).He is struggling to maintain his blood sugar within normal limits. Edward also suffers from obesity and has been unable to control his weight with diet and exercise. He asks you if his problem is due to genetics. He points out that his mother also had type 2 diabetes and was obese. He also asks why his identical twin brother, Edgar, does not have diabetes even though they share genes and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT