Question

In: Accounting

Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased...

Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased the tile and the contractor will be reimbursed for labor only. The contractor assumes he can complete one room per day at eight hours per day and at a cost of $1000/day or $1000 per room The planned cost is $40,000 and the planned duration is 40 days Current status At the end of 6 weeks (30 days).

The contractor has completed 24 rooms at a cost of 27,000. This includes a freak accident where the tiles for two offices had to be removed & replaced.

• Create a project status table similar to the one below and calculate the values for: PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC, TCPI

•Round any indices to two decimals

Planned value (PV)

Earned value (EV)

Actual cost (AC)

Budget at Completion (BAC)

Estimate to Complete (ETC)

Variance at Completion (VAC)

To Complete Performance Index (TCPI)

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI)

Schedule Performance Index (SPI)

Estimate at Completion (EAC)

Solutions

Expert Solution

Total rooms to be tiled 40
Per day completion 1
Total laboyr hours per day 8
Charge per day/Room $1,000
Planned Cost $40,000
Planned Duration 40 Days
Current Status 6 weeks/30 Days
Rooms Completed 24
Cost 27000
Planned value (PV) Percent Complete (planned)* Task Budget $30,000
Earned value (EV) Percent Complete (Actual)* Task Budget $24,000
Actual cost (AC) Actual cost of the task $27,000
Budget at Completion (BAC) Project Budget $40,000
Estimate to Complete (ETC) EAC-AC $18,000
Variance at Completion (VAC) BAC-EAC ($5,000)
To Complete Performance Index (TCPI) (BAC-EV)/(BAC-AC) 1.23
Cost Variance (CV) EV-AC          (3,000)
Schedule Variance (SV) EV-PV ($3,000)
Cost Performance Index (CPI) Earned value/actual cost 0.89
Schedule Performance Index (SPI) EV/PV 0.8
Estimate at Completion (EAC) BAC/CPI $45,000

Related Solutions

Edward Foster is a building contractor. He and his customer have agreed that he will submit...
Edward Foster is a building contractor. He and his customer have agreed that he will submit a bill to them when he is 25 percent complete, 50 percent complete, 75 percent complete, and 100 percent complete. For example, he has a $200,000 room addition. When he has completed 25 percent, he will bill his customer $50,000. The problem occurs when he is 40 percent complete, has incurred expenses but cannot yet bill his customer. How can his revenue and expenses...
Owner of an auto repair shop hires Contractor to remodel his shop but does not mention...
Owner of an auto repair shop hires Contractor to remodel his shop but does not mention that two days after the scheduled completion date, Owner is to receive five small US Army personnel carrier trucks for service, with a three-week deadline to finish the job and turn the trucks over to the army. The contract between Owner and the army has a liquidated damages clause calling for $300 a day for every day trucks are not operable after the deadline....
A small industrial contractor purchased a warehouse building for storing equipment and materials that are not...
A small industrial contractor purchased a warehouse building for storing equipment and materials that are not immediately needed at construction job sites. The cost of the building was $100,000 and the contractor has just made an agreement with the seller to finance the purchase over a 5-year period. The agreement state that monthly payments will be made based on a 30-year amortization, but the balance owed at the end of year 5 must be paid in a lump-sum "balloon" payment....
d) A building contractor calls the project office and asks if the necessary funds have been...
d) A building contractor calls the project office and asks if the necessary funds have been secured for construction work to begin. What document is required from the project company to the construction company for works to begin?
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction...
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction work commenced on April 1, 2020, and it is expected to continue through July 31, 2022, the estimated completion date. Reed made progress payments to the contractor in 2020 as follows: Date Amount April 1 $ 48,000 June 1 195,000 September 1 322,000 November 1 67,000 $632,000 As stated in A5 above, Reed took a 1-year, 9%, $225,000 construction loan to help fund the...
d) A building contractor calls the project office and asks if the necessary funds have been...
d) A building contractor calls the project office and asks if the necessary funds have been secured for construction work to begin. What document is required from the project company to the construction company for works to begin?
You are field manager for the general contractor on a multi-story office building under construction. The...
You are field manager for the general contractor on a multi-story office building under construction. The project has risen all 15 floors above the foundation. The roof is on and the exterior façade of the structure, consisting of alternating blue glass ribbon windows and red granite panels, has “dried in” the project many weeks ago. On the third, seventh and fifteenth floors, the executive offices located on the corners of the building have blue glass doors that lead outside to...
You are the owner of a 65,000 square foot office building. You purchased the building five...
You are the owner of a 65,000 square foot office building. You purchased the building five years ago for $11,500,000. During that entire time the building was triple net leased to a tenant who was also responsible for all maitenance and capital upkeep. The net rent the tenant paid was flat at $12.50 per square foot per year. You have just negotiated a lease extension which will raise the rent to $14.00 per square foot for the next 10 years....
An office building for use in the business. It was purchased on 15 June CY at...
An office building for use in the business. It was purchased on 15 June CY at a cost of $770,000. Construction had commenced on 1 March 1987 at a cost of $300,000. Calculate the Division 43 deductions which are available to the taxpayer. CY is current year
A building contractor buys 80% of his cement from supplier A and 20​% from supplier B....
A building contractor buys 80% of his cement from supplier A and 20​% from supplier B. A total of 75​% of the bags from A arrive​ undamaged, while 85​% of the bags from B arrive undamaged. Find the probability that a damaged bag is from supplier Upper A.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT