Question

In: Finance

5. Brandt Enterprises is considering a new project that has an estimated NPV of $800. The...

5. Brandt Enterprises is considering a new project that has an estimated NPV of $800. The assistant to CFO conducted a sensitivity analysis with regard to sales price and salvage value. The results are documented in the table below: Sales price change by -30% -15% 0 15% 30% NPV results 579.2 724 800 876 1051.2 Salvage value change by -30% -15% 0 15% 30% NPV results 624 780 800 820 984 The assistant needs to explain what sensitivity is and what the results mean. Can you help to explain the above two issues?

Solutions

Expert Solution

The technique used to determine how independent variable values will impact a particular dependent variable under a given set of assumptions is defined as sensitive analysis. For example if the sales fall by 10%, by how much amount would the profits change. Or if the variable costs decreases by a certain percentage, how much would the change be in profits. Basically sensitivity analysis is a risk management tool, helping management understand the change in input values would have on Output.

It is also known as the what – if analysis.

Sensitivity results

Salvage Value

A better way to represent sensitivity is given below. A 30% decrease in salvage value of equipment would lead to a 22% decrease in NPV. An increase of 15% in salvage value over the base value, will increase the NPV by a mere 2.50%

Sensitivity of Salvage Value
Variation in Salvage NPV % Change in NPV
-30%                                 624 -22.00%
-15%                                 780 -2.500%
0%                                 800                                       -  
15%                                 820 2.50%
30%                                 984 23.00%

Sales Price

A better way to represent sensitivity is given below. A 30% increase in sales price would lead to a 31.40% increase in NPV. A decrease of 15% in sales price over the base value, will decrease the NPV by 9.50%

Sensitivity of Sales Price
Variation in Unit Price NPV % Change in NPV
-30%                                 579 -27.60%
-15%                                 724 -9.500%
0%                                 800                                       -  
15%                                 876 9.50%
30%                              1,051 31.40%

NPV is more sensitive to changes in Sales price than to changes in Salvage Value


Related Solutions

Brandt Enterprises is considering a new project that has an estimated cost of $900,000 and cash...
Brandt Enterprises is considering a new project that has an estimated cost of $900,000 and cash inflows of $286,000 each year in next 5 years. The project’s WACC is 8%. After estimating the cash flows of the project, the CFO conducted a scenario analysis and found the CV (coefficient of variation) of the project’s NPV is 3.8 Given that the CV of an average project of the company is in the range of 1.0 to 2.0, how will you interpret...
A firm has estimated its cost of capital as 5% and is considering a project with...
A firm has estimated its cost of capital as 5% and is considering a project with an initial investment of -$265,000. The subsequent cash flows are $65,000; $77,000; $83,000; $91,000; and $96,000. In the final year (year #6), the firm must pay $50,000 to clean up the site. Calculate the project’s MIRR using the three methods discussed in class. Please provide timelines, a description of all of your math, and calculator inputs.
Problem 10-12 NPV and Modified ACRS [LO1] Quad Enterprises is considering a new three-year expansion project...
Problem 10-12 NPV and Modified ACRS [LO1] Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.79 million. The fixed asset falls into the three-year MACRS class. The project is estimated to generate $2,110,000 in annual sales, with costs of $799,000. The project requires an initial investment in net working capital of $330,000, and the fixed asset will have a market value of $225,000 at the end of the project.    If...
Margarite’s Enterprises is considering a new project. The project will require $200,000 for new fixed assets...
Margarite’s Enterprises is considering a new project. The project will require $200,000 for new fixed assets and $15,000 for additional investments in net working capital. The project has a 3-year life. The fixed assets will be depreciated using 3-year MACRS to a zero book value over the life of the project. At the end of the project, the fixed assets can be sold for 5 percent of their original cost. The net working capital returns to its original level at...
show work Margarite’s Enterprises is considering a new project. The project will require $250,000 for new...
show work Margarite’s Enterprises is considering a new project. The project will require $250,000 for new fixed assets and $11,000 for additional investments in net working capital. The project has a 3-year life. The fixed assets will be depreciated using 3-year MACRS to a zero book value over the life of the project. At the end of the project, the fixed assets can be sold for 4 percent of their original cost. The net working capital returns to its original...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($44 million) Below average 0.20 (12 million) Average 0.50 12 million Above average 0.20 20 million Boom 0.05 36 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 - $80 million Below average 0.20 - $26 million Average 0.50 12 million Above average 0.20 14 million Boom 0.05 30 million Calculate the project's expected NPV, standard deviation,...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 - $54 million Below average 0.20 - $14 million Average 0.50 12 million Above average 0.20 20 million Boom 0.05 28 million Calculate the project's expected NPV, standard deviation,...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 - $74 million Below average 0.20 - $28 million Average 0.50 12 million Above average 0.20 18 million Boom 0.05 26 million Calculate the project's expected NPV, standard deviation,...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($68 million) Below average 0.20 (14 million) Average 0.50 12 million Above average 0.20 18 million Boom 0.05 30 million Calculate the project's expected NPV, standard deviation, and coefficient...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT