In: Finance
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:
Economic Scenario | Probability of Outcome | NPV |
Recession | 0.05 | - $54 million |
Below average | 0.20 | - $14 million |
Average | 0.50 | 12 million |
Above average | 0.20 | 20 million |
Boom | 0.05 | 28 million |
Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two decimal places.
E(NPV): $ million
σNPV: $ million
CV:
1)The project's expected NPV is the sum of the product of probability and respective NPV of all the economic scenarios:
Economic scenario | Probability of outcome(P) | NPV | P * NPV |
Recession | 0.05 | -54 | -2.7 |
Below average | 0.2 | -14 | -2.8 |
Average | 0.5 | 12 | 6 |
Above average | 0.2 | 20 | 4 |
Boom | 0.05 | 28 | 1.4 |
Total | 5.9 |
Hence, E(NPV): $ 5.9 million
2)
Economic scenario | Probability of outcome(P) | NPV | P * NPV | X=(NPV - Expected NPV) | X^2 | P * (X^2) |
Recession | 0.05 | -54 | -2.7 | -59.9 | 3588.01 | 179.4005 |
Below average | 0.2 | -14 | -2.8 | -19.9 | 396.01 | 79.202 |
Average | 0.5 | 12 | 6 | 6.1 | 37.21 | 18.605 |
Above average | 0.2 | 20 | 4 | 14.1 | 198.81 | 39.762 |
Boom | 0.05 | 28 | 1.4 | 22.1 | 488.41 | 24.4205 |
Expected NPV | 5.9 | Variance | 341.39 |
Standard deviation = sqrt (variance) = sqrt (341.39) =18.48
σNPV: $ 18.48 million
3)
coefficient of variation = Standard dev / mean
= 18.48/ 5.9
= 3.13
CV= 3.13