In: Finance
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:
Economic Scenario | Probability of Outcome | NPV |
Recession | 0.05 | ($44 million) |
Below average | 0.20 | (12 million) |
Average | 0.50 | 12 million |
Above average | 0.20 | 20 million |
Boom | 0.05 | 36 million |
Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your answers to two decimal places. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13.
E(NPV) | = $ ____million |
?NPV | = $ ____million |
CV | = _____ |
Expected NPV
Expected NPV = sum of (Probability x NPV)
or, Expected NPV = 0.05 x - 44 million + 0.20 x - 12 million + 0.50 x 12 million + 0.20 x 20 million + 0.05 x 36 million
or, Expected NPV = $7.20 million
Standard Deviation
or, Standard Deviation = $17.0458206021 million or $17.05 million
Coefficient of Variation (CV)
CV = Standard Deviation / Expected NPV = $17.05 million / $7.20 million = 2.368055 or 2.37