Question

In: Finance

You are comparing two projects. One is a four-year project costing $1 million and will provide...

You are comparing two projects. One is a four-year project costing $1 million and will provide benefit of $500K/year. The second is an eight-year project with annual CFs of $500K/year and an initial cost of $1.5 million. If there is a 70% chance the cost of the first project will drop by 30% after the first four years and the remaining cash flows stay at $500K/year, which project is the better choice? The discount rate is 10%.

Solutions

Expert Solution

NPV = PV of Cash Inflows - PV of Cash Outflows

PV of Cash Inflows = Cash Inflow1 / (1 + Discount Rate)1 + Cash Inflow2 / (1 + Discount Rate)2 + ...... + Cash Inflown / (1 + Discount Rate)n

The manager should choose Project 2 because NPV of Project 2 is higher than NPV of Project 1.


Related Solutions

Suppose an economy is made up of four one-year projects with each project costing $1,000,000. Project...
Suppose an economy is made up of four one-year projects with each project costing $1,000,000. Project Future Value ($) One 1,111,000 Two 1,085,000 Three 1,060,000 Four 1,035,000 1. Assuming investors use the NPV criteria to choose investment projects, how much investment (in millions) will there be if the interest rate is 0.05?   (If your answer is $1 million, then enter 1.) 2. If interest rates are 0.05 then savings available for investment is $3 million. What is the difference between...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A - $ 100 $26 $28 $42 $52 B -$ 100    $52 $42 $28    $18 a. What is the IRR of each? project? b. What is the NPV of each project at your cost of? capital? c. At what cost of capital are you indifferent between the two? projects? d. What should you? do?
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -29 -45 1 30 45 2 40 50 3 50 50 The appropriate discount rate is 9%. Part 1 What is the NPV of project A (in $ million)? Part 2 What is the NPV of project B (in $ million)?
You have two potential investment projects, Project A and Project B. You can take one, but...
You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are: Year 0 1 2 3 Project A Cash Flow -$50,000 $45,000 $5,000 $5,000 Project B Cash Flow -$50,000 $5,000 $5,000 $50,000 a. Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%.   Which project would you take, and why? c)  Compute the NPV for each...
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000....
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000. 1 600. 800. 2 800. 600. 3 1,200. 200. 4 Each project has a cost of $ 2,000 and the total cost of capital is 10%. Determine which project should be accepted ?Using Net present value (NPV)
The following are the cash flows of two projects: Year    Project A    Project B...
The following are the cash flows of two projects: Year    Project A    Project B 0 -250    -250 1    130    150 2    130    150 3    130    150 4    130 If the opportunity cost is 10%, what is the profitability index for each project? Project Profitability Index A B   
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT