Question

In: Finance

You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...

You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back faster c. Project A; because it has the higher net present value d. Project B; because it has the higher profitability index e. Project A; because it has the higher profitability index

Solutions

Expert Solution

Year Project A Project B
0 -10000 -20000
1 3000 5000
2 8000 7000
3 4000 12000
4 2000 10000

Cash Flow for Year n = CFn

Required Return = r = 12%

NPV = Σ CFn/(1+r)n

NPVA = -10000 + 3000/(1+0.12) + 8000/(1+0.12)2 + 4000/(1+0.12)3 + 2000/(1+0.12)4 = $3174.28

NPVB = -20000 + 5000/(1+0.12) + 7000/(1+0.12)2 + 12000/(1+0.12)3 + 10000/(1+0.12)4 = $4941.19

Profitability Index PI = PV of future cash flows / Initial investment = (NPV + Initial investment) / Initial Investment

PIA = (3174.28 + 10000)/10000 = 1.32

PIB = (4941.19 + 20000)/20000 = 1.25

To find payback period, let us find the cumulative cash flows -

Year Project A Cumulative A Project B Cumulative B
0 -10000 -10000 -20000 -20000
1 3000 -7000 5000 -15000
2 8000 1000 7000 -8000
3 4000 5000 12000 4000
4 2000 7000 10000 14000

Payback period is the period when the cumulative cash flow becomes positive

Payback for Project A = 1 + 7000/8000 = 1.88 years

Payback for Project B = 2 + 8000/12000 = 2.67 years

Of all the rules, NPV rule should be considered first

Hence, "a. Project B; because it has the higher net present value" is the correct answer option


Related Solutions

You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000...
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000 -$3,300,000 1 1,940,000 866,000 2 1,350,000 1,250,000 3 850,000 2,325,000 The firm uses a discount rate of 12.628%. At that discount rate we find that A-Project A is clearly preferred B-Project B is clearly preferred C-the projects have roughly the same NPV's Given that finding, the firm should select ___________because it's NPV is the least sensitive to change A-Project A B-Project B
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000    a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: Years Project B: Years a-2. If the company's payback period is two years, which, if either, of these projects should be...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,300 –$ 8,700 1 7,500 3,400 2 6,500 2,900 3 2,100 5,300 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project A Project B If the appropriate discount rate is 12...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,800 –$ 9,200 1 8,400 3,900 2 7,000 3,400 3 2,100 5,800 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B Project A If the appropriate discount rate is 10...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT