Question

In: Finance

The following are the cash flows of two projects: Year    Project A    Project B...

The following are the cash flows of two projects:

Year    Project A    Project B

0 -250    -250

1    130    150

2    130    150

3    130    150

4    130

If the opportunity cost is 10%, what is the profitability index for each project?

Project Profitability Index

A

B

  

Solutions

Expert Solution

Project A

Year

Cashflow

PV Factor @ 10%

PV

0

-250

1

$ -250.00

1

130

                     0.9091

$   118.18

2

130

                     0.8264

$   107.44

3

130

                     0.7513

$     97.67

4

130

                     0.6830

$     88.79

NPV

$   162.08

Profitability Index = Initial Investment + NPV/ Initial Investment

                                  =$250 +162.08/$250

                                   =$412.08/$250

                                =          1.65

Project B

Year

Cashflow

PV Factor @ 10%

PV

0

-250

1

$ -250.00

1

150

                     0.9091

$   136.36

2

150

                     0.8264

$   123.97

3

150

                     0.7513

$   112.70

NPV

$   123.03

Profitability Index = Initial Investment + NPV/ Initial Investment

                                  =$250 +$123.03/$250

                                   = $ 373.03 /$250

                                =          1.49

Project

Profitability Index

A

                             1.65

B

                             1.49


Related Solutions

The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330 ) $ (330 ) 1 160 230 2 160 230 3 160 230 4 160 a. If the opportunity cost of capital is 12%, calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. Which of these projects is worth pursuing? ****NOTE**** You are finding the NPV, NOT the Profitability index!
The following are the cash flows of two projects: Year Project A Project B 0 $(340)...
The following are the cash flows of two projects: Year Project A Project B 0 $(340) $(340) 1 170 240 2 170 240 3 170 240 4 170 A.) Calculate the NPV for both projects if the opportunity costs of capital is 15%. *(2 decimal places, do not round intermediate calculations) B.) Suppose you can choose one one of these projects, which would you choose?
The following are the cash flows of two projects: Year Project A Project B 0 −$330...
The following are the cash flows of two projects: Year Project A Project B 0 −$330        −$330        1 160        230        2 160        230        3 160        230        4 160        a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV         A $    B    b. Suppose that you can choose only one of...
The following are the cash flows of two projects: Year Project A Project B 0 -290...
The following are the cash flows of two projects: Year Project A Project B 0 -290 -290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index a b
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT