In: Economics
Suppose an economy is made up of four one-year projects with
each project costing $1,000,000.
Project | Future Value ($) |
One | 1,111,000 |
Two | 1,085,000 |
Three | 1,060,000 |
Four | 1,035,000 |
1. Assuming investors use the NPV criteria to choose investment
projects, how much investment (in millions) will there be if the
interest rate is 0.05?
(If your answer is $1 million, then enter
1.)
2. If interest rates are 0.05 then savings available for investment
is $3 million.
What is the difference between Investment (I) and Savings (S) in
millions (i.e. I - S) ?
3. If the country's demand for investment is I = 30 - 181*i, what
is investment (I) if i=0.12?
4. If the country's supply of savings is S = 4 + 104*i, what is
savings (S) if i=0.12??
5. For I and S, in #3 & #4, at what interest rate is
I=S?
Solution:
1. Present value, PV = FV/(1+i)
Net present value = PV - cost of project
Further, investment takes place in the project if net present value is positive. Then,
For project 1, NPV = 1,111,000/(1 + 0.05) - 1000000 = 58,095.24 > 0
For project 2, NPV = 1,085,000/(1 + 0.05) - 1000000 = 33,333.33 > 0
For project 3, NPV = 1,060,000/(1 + 0.05) - 1000000 = 9,523.81 > 0
For project 4, NPV = 1,035,000/(1 + 0.05) - 1000000 = -14,285.71 < 0
So, investment in 3 projects takes place (in last project, NPV is negative). Thus, total investment = total cost in 3 projects = 3*$1m = $3m
2. At interest rate of 0.05, S = $3m
So, I - S = $3m - $3m = 0
3. With country's demand for investment as I = 30 - 181*i
If i = 0.12, I = 30 - 181*0.12
I = 30 - 21.72 = $8.28m
4. With country's savings function as S = 4 + 104*i
if i = 0.12, S = 4 + 104*0.12
S = 4 + 12.48 = $16.48m
5. Finding i for which I = S
30 - 181*i = 4 + 104*i
30 - 4 = i*(104 + 181)
i = 26/285 = 0.0912
So, for interest rate of 9.12%, S = I