In: Finance
You are considering the following two mutually exclusive projects.
YEAR PROJECT (A) PROJECT (B)
0 -$35,000 -$35,000
1 22,000 13,000
2 20,000 21,000
3 13,000 22,000
What is the internal rate of return of PROJECT A?
IRR
IRR is the rate at which NPV of the project become zero, Computing the internal rate of return (IRR) for a possible investment is time-consuming and inexact. IRR calculations must be performed via guesses, , and trial and error. Essentially, an IRR calculation begins with two random guesses at possible values and ends with either a validation or rejection. If rejected, new guesses are necessary.
Here,
0 = PV of cash inflow - PV of cash outflow
We can solve through this trail and error method
For calculating IRR, we need two NPV with their discount rate. One of them is positive and one of them negative. And discount rate used for those NPVs are one of them lower than IRR and one of them Higher than IRR
The first step is to make guesses at the possible values for lower discount rate and higher discount rate to determine
For correcting Guess just use fake payback period and check the closest value of the result in the Present value of annuity $ 1 factor table’s 3 year period row and find the correspondent rate on top of that row. Use this rate as apprpx.IRR and take two rate, one is lower than this rate and one is higher than this rate
Fake payback period = initial investment / average CF
Fake payback period = 35000 / (22000 + 20000 + 13000) / 3
Fake payback period = 35000 / 18333 = 1.909
Look In the table and find the closest value of 1.909 and its rate on top of the column
Closest value = 1.8955 aand its correspondent rate is 27%
So, pretend that 27% is the IRR take two rate, one is below 27% and one is higher than 27% . I have taken here 20% and 30%
Use 20% discount rate and find the NPV of the project. It should be positive.
NPV @ 20%
Year |
CF |
PV factor $1 @ 20% |
CF * PV factor $1 @ 20% |
0 |
- $ 35000 |
(1 / 1+20%)0 = 1 |
-35000 |
1 |
22000 |
(1 / 1+20%)1 = 0.8333 |
18332.6 |
2 |
20000 |
(1 / 1+20%)2 = 0.6944 |
13888 |
3 |
13000 |
(1 / 1+20%)3 = 0.5787 |
7523.15 |
NPV = PV of CF - initial investment
NPV = 18332.6 + 13888 + 7523.15 - 35000 = 4743.75 (positive NPV)
One of thing that if we get a positive NPV, the discount rate used here be lower than IRR
Use 30% discount rate and find the NPV of the project. It should be positive.
NPV @ 30%
Year |
CF |
PV factor $1 @ 20% |
CF * PV factor $1 @ 20% |
0 |
- $ 35000 |
(1 / 1+30%)0 = 1 |
-35000 |
1 |
22000 |
(1 / 1+30%)1 = 0.769 |
16318 |
2 |
20000 |
(1 / 1+30%)2 = 0.592 |
11840 |
3 |
13000 |
(1 / 1+30%)3 = 0.455 |
5917.15 |
NPV = PV of CF - initial investment
NPV = 16318 + 11840 + 5917.15 - 35000 = -325 (negative NPV)
One of thing that if we get a negative NPV, the discount rate used here be higher than IRR
So we can conclude that the IRR is between 20% and 30%
***Next use a formula to find correct IRR
IRR = Lower discount rate + (NPV @ Lower discount rate / Difference between two NPV ) * ( Higher discount rate - Lower discount rate)
Here,
Lower discount rate = 20%
NPV @ Lower discount rate = 4743.75
Difference between two NPV = NPV @ Lower discount rate - NPV @ Higher discount rate
Difference between two NPV = 4743.75 - (- 325) = 5068.59
NPV @ Higher discount rate = - 325
Higher discount rat = 30%
Put the values to the formula
IRR = 20% + ( 4743.75 / 5068.59 ) * ( 30% - 20%)
IRR = 20% + 0.9359 * 10
IRR = 20% + 9.36 = 29.36%
The correct IRR is = 29.36%