Question

In: Finance

You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&

You are considering the following two mutually exclusive projects.

YEAR             PROJECT (A)         PROJECT (B)   

    0                  -$35,000                  -$35,000

    1                     22,000                     13,000

    2                     20,000                     21,000

    3                     13,000                     22,000

What is the internal rate of return of PROJECT A?

Solutions

Expert Solution

IRR

IRR is the rate at which NPV of the project become zero, Computing the internal rate of return (IRR) for a possible investment is time-consuming and inexact. IRR calculations must be performed via guesses, , and trial and error. Essentially, an IRR calculation begins with two random guesses at possible values and ends with either a validation or rejection. If rejected, new guesses are necessary.

Here,

0 = PV of cash inflow - PV of cash outflow

We can solve through this trail and error method

For calculating IRR, we need two NPV with their discount rate. One of them is positive and one of them negative. And discount rate used for those NPVs are one of them lower than IRR and one of them Higher than IRR

The first step is to make guesses at the possible values for lower discount rate and higher discount rate to determine

For correcting Guess just use fake payback period and check the closest value of the result in the Present value of annuity $ 1 factor table’s 3 year period row and find the correspondent rate on top of that row. Use this rate as apprpx.IRR and take two rate, one is lower than this rate and one is higher than this rate

Fake payback period = initial investment / average CF

Fake payback period = 35000 / (22000 + 20000 + 13000) / 3

Fake payback period = 35000 / 18333 = 1.909

Look In the table and find the closest value of 1.909 and its rate on top of the column

Closest value = 1.8955      aand its correspondent rate is 27%

So, pretend that 27% is the IRR take two rate, one is below 27% and one is higher than 27% . I have taken here 20% and 30%

Use 20% discount rate and find the NPV of the project. It should be positive.

NPV @ 20%

Year

CF

PV factor $1 @ 20%

CF * PV factor $1 @ 20%

0

- $ 35000

(1 / 1+20%)0 = 1

-35000

1

22000

(1 / 1+20%)1

= 0.8333

18332.6

2

20000

(1 / 1+20%)2

= 0.6944

13888

3

13000

(1 / 1+20%)3

= 0.5787

7523.15

NPV = PV of CF - initial investment

NPV = 18332.6 + 13888 + 7523.15 - 35000 = 4743.75 (positive NPV)

One of thing that if we get a positive NPV, the discount rate used here be lower than IRR

Use 30% discount rate and find the NPV of the project. It should be positive.

NPV @ 30%

Year

CF

PV factor $1 @ 20%

CF * PV factor $1 @ 20%

0

- $ 35000

(1 / 1+30%)0 = 1

-35000

1

22000

(1 / 1+30%)1

= 0.769

16318

2

20000

(1 / 1+30%)2

= 0.592

11840

3

13000

(1 / 1+30%)3

= 0.455

5917.15

NPV = PV of CF - initial investment

NPV = 16318 + 11840 + 5917.15 - 35000 = -325 (negative NPV)

One of thing that if we get a negative NPV, the discount rate used here be higher than IRR

So we can conclude that the IRR is between 20% and 30%

***Next use a formula to find correct IRR

IRR = Lower discount rate + (NPV @ Lower discount rate / Difference between two NPV ) * ( Higher discount rate - Lower discount rate)

Here,

Lower discount rate = 20%

NPV @ Lower discount rate = 4743.75

Difference between two NPV = NPV @ Lower discount rate - NPV @ Higher discount rate

Difference between two NPV = 4743.75 - (- 325) = 5068.59

NPV @ Higher discount rate = - 325

Higher discount rat = 30%

Put the values to the formula

IRR = 20% + ( 4743.75 / 5068.59 ) * ( 30% - 20%)

IRR = 20% + 0.9359 * 10

IRR = 20% + 9.36 = 29.36%

The correct IRR is = 29.36%


Related Solutions

You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000...
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000 -$3,300,000 1 1,940,000 866,000 2 1,350,000 1,250,000 3 850,000 2,325,000 The firm uses a discount rate of 12.628%. At that discount rate we find that A-Project A is clearly preferred B-Project B is clearly preferred C-the projects have roughly the same NPV's Given that finding, the firm should select ___________because it's NPV is the least sensitive to change A-Project A B-Project B
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
Novell, Inc., has the following mutually exclusive projects. Year Project A. Project B __ __ 0...
Novell, Inc., has the following mutually exclusive projects. Year Project A. Project B __ __ 0 22, 000 25,000 1 13,000 14,000 2 9,500 10,500    3 3,100 9,500 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g. 32.161.) Project A. _____ years Project B ______ years a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? (Choose the...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000    a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: Years Project B: Years a-2. If the company's payback period is two years, which, if either, of these projects should be...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT