Question

In: Finance

You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project...

You've estimated the following cash flows (in $ million) for two mutually exclusive projects:

Year Project A Project B
0 -29 -45
1 30 45
2 40 50
3 50 50

The appropriate discount rate is 9%.

Part 1

What is the NPV of project A (in $ million)?

Part 2

What is the NPV of project B (in $ million)?

Solutions

Expert Solution

Part 1 – Net Present Value (NPV) of PROJECT A

Year

Annual Cash Flow

($ in Million)

Present Value factor at 9%

Present Value of Cash Flow ($ in Million)

1

30

0.91743

27.52

2

40

0.84168

33.67

3

50

0.77218

38.61

TOTAL

99.80

Net Present Value = Present Value of the annual cash inflows - Initial Investment

= $99.80 Million - $29 Million

= $70.80 Million

Part 2 – Net Present Value (NPV) of PROJECT B

Year

Annual Cash Flow

($ in Million)

Present Value factor at 9%

Present Value of Cash Flow ($ in Million)

1

45

0.91743

41.28

2

50

0.84168

42.08

3

50

0.77218

38.61

TOTAL

121.98

Net Present Value = Present Value of the annual cash inflows - Initial Investment

= $121.98 Million - $45 Million

= $76.98 Million

NOTE

The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.


Related Solutions

You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 90,000 1) Calculate NPV of each project if the required rate of return on these projects is 8 percent. 2) which would be chosen and why?
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project...
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project A Cash Flow                      Project B Cash Flow 0                              -$10,000                                             -$8,000 1                                   1000                                                7000 2                                   2000                                                1000             3                                   6000                                                1000 4                                   6000                                                1000 If the company’s required rate of return is 10%, find the project’s NPV, IRR, PI, and payback period. Which project they should invest in?
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A...
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A Project B 0 ? 120 ? 120 1 50 69 2 70 69 3 90 69 a-1. What is the NPV of each project if the opportunity cost of capital is 2%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) b-1. What is the NPV of each project if the opportunity cost of capital is 14%? (Do not round intermediate...
Your firm has estimated the following cash flows for two mutually exclusive capital investment projects. The...
Your firm has estimated the following cash flows for two mutually exclusive capital investment projects. The firm's required rate of return is 13%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 -$100,000 -$100,000 1 28,900 48,000 2 28,900 40,000 3 28,900 40,000 4 28,900 5 28,900 Which of the following statements best describes projects A and B? a) Project A should be accepted because it has the highest NPV. b)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT