In: Accounting
Required information
[The following information applies to the questions displayed below.]
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 20,000 units, which took 41,000 machine hours. Actual fixed factory overhead costs for the year amounted to $245,000, while the actual variable overhead cost per unit was $3.90.
Based on the information provided above, provide the correct summary journal entries for actual and applied factory overhead costs (both variable and fixed) for the year. Assume that the company uses a single account, Factory Overhead, to record both actual and applied factory overhead. Also, assume that the only variable overhead cost was electricity and that actual fixed overhead consisted of depreciation of $150,000 and supervisory salaries of $95,000. Finally, assume that both electricity expense and the supervisory salaries expense have been incurred but not yet paid (i.e., both are current liabilities). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Journal Entries
A
Record the actual overhead costs.
B
Record the overhead costs applied to production.
C
Record the factory overhead variances.
D
Record the entry to close the variance accounts to cost of goods sold.
E
Record the entry to close the variance accounts to Work in process inventory, Finished goods inventory, and Cost of goods sold.
Account | Debit | Credit |
Overhead incurred | 323,000 | |
Wages payable | 95,000 | |
Depreciation expense | 150,000 | |
Electricity payable | 78,000 | |
(to record actual overhead) | ||
Work in process | 280,000 | |
Overhead applied | 280,000 | |
(to record applied overhead) | ||
Overhead applied | 280,000 | |
Overhead cost variance | 43,000 | |
Overhead incurred | 323,000 | |
(entry to record variance) | ||
Cost of goods sold | 43,000 | |
Overhead cost variance | 43,000 | |
(entry to close variances) |
Particulars | Amount | Particulars | Amount | |
Estimated fixed overhead | 250,000 | Units produced | 20000 | |
Divided by | 25,000 | × rate per unit | 14 | |
Rate per unit | 10 | OH applied | 280,000 | |
Add: variable OH per unit | 4 | OH actual | 323,000 | |
Total OH rate per unit | 14 | OH under applied | 43,000 |