Earned Value Management (EVM) is a tool to measure project
performance against the project baseline. It helps monitoring
project performance from both a cost and schedule perspective. Both
these factors impact the overall project cost.
Earned value require the following parameters/ inputs:
- Planned Value (PV) = Budgeted amount of a
given period
- Actual Cost (AC) = actual costs till date
- Earned Value (EV) = total project budget
multiplied by the % of project completion
The above parameters are readily available to the Project
Manager.
- Schedule Performance Index (SPI) : SPI =
EV/PV
SPI measures progress achieved against progress planned. An
SPI value <1.0 indicates less work was completed than planned
effort. SPI >1.0 indicates more work was completed than planned
effort.
- Cost Performance Index (CPI) : CPI =
EV/AC
CPI measures the value of work completed against the actual
cost. A CPI value <1.0 indicates costs were higher than budgeted
for. CPI >1.0 indicates costs were less than budgeted
for.
Note:
- For both SPI and CPI, >1 is good, and <1 is not
good.
- Schedule variance = EV-PV, and cost variance =
EV–AC.
- Subtracting can quickly be done in your head, and for these
cases, >0 is good, and <0 is not good. But unlike SPI and
CPI, variance cannot be effectively compared across projects or
over time, where the budget for a project may have changed, because
they’re relative to the size of the project.
- Estimated at Completion (EAC) : EAC = (Total
Project Budget)/CPI
EAC is a forecast of how much the total project will
cost.
Example |
|
|
|
Project |
ABC |
|
|
Duration |
1
year |
|
|
1
year Budget (Overall Project cost) |
$100,000 |
|
|
Half yearly Budget milestone (PV) |
$55,000 |
|
|
Planned Value (PV) at 6 months |
$55,000 |
|
|
Actual Cost (AC) at 6 months |
$45,000 |
|
|
|
|
|
|
|
|
|
|
Parameters |
Formula |
Value (Output) |
Inferences derived |
Earned Value (EV) |
($100,000 * 0.5) |
$50,000 |
|
Schedule Variance (SV) |
EV–PV = $50,000-$55,000 |
-$5,000 |
(bad because <0) |
Schedule Performance Index (SPI) |
EV/PV = $50,000/$55,000 |
0.91 |
(bad because <1) |
Cost Variance (CV) |
EV–AC = $50,000-$45,000 |
$5,000 |
(good because >0) |
Cost Performance Index (CPI) |
EV/AC = $50,000/$45,000 |
1.11 |
(good because >1) |
Estimated at Completion (EAC) |
(Total Project Budget)/CPI = $100,000/1.11 |
$90,000 |
|
Additional inferences from the analysis:
- Because SV is negative and SPI is <1, the project is
considered behind schedule. We’re 50% of the way through the
project but have planned for 55% of the costs to be used. There
will have to be some catch-up in the second half of the
project.
- Because CV is positive and CPI is >1, the project is
considered to be under budget. We’re 50% of the way through the
project, but our costs so far are only 45% of our budget. If the
project continues at this pace, then the total cost of the project
(EAC) will be only $90,000, as opposed to our original budget of
$100,000.
Human factors in Evaluation and control:
- Project Management decision-making process involves evaluation
of the alternative courses or solutions identified to solve the
problem. Alternatives have to be evaluated in the light of the
objectives to be achieved and the resources required and assigned.
Evaluation involves a through scrutiny of the relative merits and
demerits of each of the alternatives in relation to the objectives
sought to be achieved by solving the problem and working towards
achieving budget
- Continue to motivate employees in a new environment through a
system of evaluation and rewards, as employee attitudes and
expectations are fast changing;
- Planning and controlling – the two functions are closely
interrelated in that while plans specify the objectives to be
achieved, control as a managerial function facilitates to know
whether the actual performance is in conformity with the planned
one. So that, in the event of deviations, appropriate corrective
measures could be taken. In the absence of adequate control
mechanism, unexpected changes in the environment may push the
organisation off the track. Thus, controlling implies measuring and
correcting the activities to ensure that events conform to
plans.
- Commitment of all people involved, all the internal and
external stakeholders, resources and employees to achieve the
planned deliverables and ensure optimized Earned value