Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the maximum labour available on any day is only 6, Find the EF for activity G
Activity | Duration | No. of men req. per day | |
A | 1 to 2 | 4 | 6 |
B | 1 to 3 | 2 | 3 |
C | 1 to 4 | 8 | 4 |
D | 2 to 6 | 6 | 3 |
E | 3 to 5 | 4 | 2 |
F | 5 to 6 | 1 | 1 |
G | 4 to 6 | 1 | 5 |
The Gantt chart for the given project is as follows:
As per requirement of only 6 employees are available per day, the schedule changes as per follows:
The improved Gantt chart is as follows:
hus, Earliest Finish time of the activity G = 19 |