Question

In: Operations Management

Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the...

Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the maximum labour available on any day is only 6, Find the EF for activity G


Activity Duration No. of men req. per day
A 1 to 2 4 6
B 1 to 3 2 3
C 1 to 4 8 4
D 2 to 6 6 3
E 3 to 5 4 2
F 5 to 6 1 1
G 4 to 6 1 5

Solutions

Expert Solution

The Gantt chart for the given project is as follows:

As per requirement of only 6 employees are available per day, the schedule changes as per follows:

The improved Gantt chart is as follows:

hus, Earliest Finish time of the activity G = 19


Related Solutions

Constraints are those factors that can limit a project. Which of the following are considered constraints...
Constraints are those factors that can limit a project. Which of the following are considered constraints (choose all that apply)? a. Quality b. Strategic Plan c. Risks d. Requirements e. People and Materials f. Project Management Information System
Create a project schedule based on task dependencies and resource constraints
Create a project schedule based on task dependencies and resource constraints
Identify three constraints imposed on an IT project schedule. Explain the impact that each of these...
Identify three constraints imposed on an IT project schedule. Explain the impact that each of these can have on project management.
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline -...
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline - B Outsourcing, sponsors, and budget - C Time, scope, and resources - D Testing, accptance, and operation - -54. Which document outlines participation by various roles in a project? -A Communication plan B- PERT chart - C Responsibility matrix D Gantt chart 55. The relationship among the variables of the triple constraints is such that if any one variable changes, at least one other...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The two major constraints that can hamper a construction project are time and resources. What actions...
The two major constraints that can hamper a construction project are time and resources. What actions can a project manager undertake to overcome these constraints?
Evaluation of an engineering project involves the following constraints ?
Evaluation of an engineering project involves the following constraints ?A) financial, environmental, social and political constraints.B) technical and financial constraints.C) technological and social constraints.D) time and money constraints. E) budget and time constraints.
Consider a project to build an amusement park. What are some of theresource constraints that...
Consider a project to build an amusement park. What are some of the resource constraints that would make this project challenging? What could you do, as a project manager, to help manage the constraints and project scheduling?
Using the constraint list in this chapter, discuss some of the primary or more common constraints with project resources and how each affects the project.
A Comprehensive Guide to Project Management Schedule and Cost Control, Ch. 6Using the constraint list in this chapter, discuss some of the primary or more common constraints with project resources and how each affects the project. Choose two of the constraints to discuss.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT