Question

In: Economics

Evaluation of an engineering project involves the following constraints ?

Evaluation of an engineering project involves the following constraints ?


A) financial, environmental, social and political constraints.

B) technical and financial constraints.

C) technological and social constraints.

D) time and money constraints. E) budget and time constraints.

Solutions

Expert Solution

The evaluation of an engineering project involves

E) Budget and time constraints

Along with budget and time, engineering projects are evaluated keeping in mind the scope of the project. These constraints form the project management triangle.


Related Solutions

Design a single stage BJT amplifier with the following constraints: This involves the following: -DC and...
Design a single stage BJT amplifier with the following constraints: This involves the following: -DC and AC analysis and the frequency response of the amplifier. -Use a 2N2222 transistor -Power supply (VCC): 6 V -An input impedance near to 3 kΩ -Overall midband voltage gain of -30 V/V -A load resistance of 2 kΩ -The input signal has an RSignal of 500 Ω -Choose a good Qpoint and select the coupling and bypass capacitors to obtain an fL-3dB of 100...
Constraints are those factors that can limit a project. Which of the following are considered constraints...
Constraints are those factors that can limit a project. Which of the following are considered constraints (choose all that apply)? a. Quality b. Strategic Plan c. Risks d. Requirements e. People and Materials f. Project Management Information System
An engineering project involves the purchase of a capital asset with first cost of $100 000,...
An engineering project involves the purchase of a capital asset with first cost of $100 000, operating costs of $5 000 per year and a service life of 10 years. The expected revenue is $20 000 per year. If the CCA rate is 25%, interest rate is 10% and the corporate tax rate is 33%, what is the project's present worth?
Choose an engineering project that involves both hydrology and hydraulics. In one paragraph, analyze ways in...
Choose an engineering project that involves both hydrology and hydraulics. In one paragraph, analyze ways in which the hydrology influences the hydraulics, and ways hydraulics influences the hydrology.
The best way to solve difficult moral issues in engineering and project evaluation is: Select one:...
The best way to solve difficult moral issues in engineering and project evaluation is: Select one: a. to ask your friends. b. to read professional textbooks. c. to read newspapers. d. to search the web. e. to consult professional engineering associations.
What sort of evaluation involves the evaluation of expressions in each part of a compound, conditional...
What sort of evaluation involves the evaluation of expressions in each part of a compound, conditional Boolean expression only as much as necessary to determine whether the expression is false? a. sequence b. sequential c. short-circuit d. smart
Engineering/ programming in MATLAB and it also involves a physics
Engineering/ programming in MATLAB and it also involves a physics
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT