Question

In: Accounting

Based on Exercise 18-33 During 2020, Kingbird Company started a construction job with a contract price...

Based on Exercise 18-33

During 2020, Kingbird Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.

2020 2021 2022
Costs incurred to date $393,900 $760,380 $1,059,000
Estimated costs to complete 616,100 341,620 –0–
Billings to date 299,000 905,000 1,610,000
Collections to date 268,000 818,000 1,421,000
2. Prepare journal entries for all 3 years.
2020 2021 2022
Contract Price $1,610,000 $1,610,000 $1,610,000
Cost incurred to date $393,900 $760,380 $1,059,000
Estimated cost yet to be incurred to complete the contract $616,100 $341,620 $0
Total cost $1,010,000 $1,102,000 $1,059,000
% of completion 39% 69% 100%
Revenue to date $627,900 $1,110,900 $1,610,000
Revenue previous year $0 $627,900 $1,110,900
Net revenue this year $627,900 $483,000 $499,100
Cost to date $393,900 $760,380 $1,059,000
Cost to date of previous year $0 $393,900 $760,380
Net cost of the year $393,900 $366,480 $298,620
Gross Profit $234,000 $116,520 $200,480

Solutions

Expert Solution

a)

2020 2021 2022
cost incurred till date 393900 760380 1059000
Estimated costs to complete 616100 341620 0
Total cost to complete 1010000 1102000 1059000
% of completion till date [cost incurred till date /total cost complete]

393900/1010000

.39 or 39%

760380/1102000

.69 or 69%

1059000/1059000

100%

Gross profit on contract [contract revenue - Total cost to complete]

1610000-1010000

=600000

1610000-1102000

=508000

1610000-1059000

=551000

2020 2021 2022
Gross profit to be recognized till date (Gross profit *% of completion) 600000*39%=234000 508000*69%=350520 551000
less:Gross profit recognized in earlier years 0 -234000 -350520
Gross profit recognized in current year 234000 116520 200480
Revenue to date

$627,900

(1610000*39%)

$1,110,900

(1610000*69%)

$1,610,000

(1610000*100%)

Revenue previous year $0 $627,900 $1,110,900
Net revenue this year $627,900 $483,000 $499,100
Cost to date $393,900 $760,380 $1,059,000
Cost to date of previous year $0 $393,900 $760,380
Net cost of the year $393,900 $366,480 $298,620
Gross Profit $234,000 $116,520 $200,480
Date Account title Debit credit
2020
1 construction in progress 393900
cash /Accounts payable 393900
(To record cost of construction)
2 Accounts receivable 299000
Billing on construction in progress 299000
(To record Billing)
3 cash 268000
Accounts receivable 268000
(To record Collections)
4 construction expense 393900
construction in progress 234000
construction revenue from long term Contract 627900
(To recognise revenue)

working :

1)Construction cost during 2020 = (393900 cost incurred till date -0 cost in prior year ) = 393900

2)Billing during the year = 299000-0 = 299000

3)collection during the year = 268000-0=268000

Date Account title Debit credit
2021
1 construction in progress 366480
cash /Accounts payable 366480
(To record cost of construction)
2 Accounts receivable 606000
Billing on construction in progress 606000
(To record Billing)
3 cash 550000
Accounts receivable 550000
(To record Collections)
4 construction expense 366480
construction in progress 116520
construction revenue from long term Contract 483000
(To recognise revenue)

working :

1)Construction cost during 2021 = (760380 cost incurred till date -393900 cost in prior year ) = 366480

2)Billing during the year = 905000-299000 = 606000

3)collection during the year = 818000-268000=550000

Date Account title Debit credit
2022
1 construction in progress 298620
cash /Accounts payable 298620
(To record cost of construction)
2 Accounts receivable 705000
Billing on construction in progress 705000
(To record Billing)
3 cash 603000
Accounts receivable 603000
(To record Collections)
4 construction expense 298620
construction in progress 200480
construction revenue from long term Contract 499100
(To recognise revenue)

working :

1)Construction cost during 2022 = (1059000 cost incurred till date -760830 cost in prior year ) = 298620

2)Billing during the year = 1610000-905000 = 705000

3)collection during the year = 1421000-818000=603000


Related Solutions

During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Your answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT