Question

In: Civil Engineering

Assume that the general contractor during the contract bidding phase notices a critical element of the...

Assume that the general contractor during the contract bidding phase notices a critical element of the wall section detail for the building is omitted. Further assume, the general contractor knows that the missing element is necessary for a successful project, required by code and will increase the cost of the project. The general contractor with knowledge of the error fails to disclose it or raise any question or request for information and bids the project believing they will be entitled to a hefty change order by raising it later. Explain how the law, ethics and morality combined with the terms of the AIA A201 General conditions should treat the General Contractor’s request for a change order for the cost of installing the missing element.

Solutions

Expert Solution

Ethically and morally it was duty of general contractor to ask the aithorities about the miasing element after knowing about that. General contractor even after having knowledge about missing part or element and its essentiallity in project did not raise any query and simply filled the bid assuming a change in order during execution of work. He should not have done it. He should have raised question about missing element so that authorities could take necessary action for same.

Further, by law as it was mistake of tender issuing authorities that they missed an essential element for completion of project therefore the general contractor is liable and entitled to have a change in order as he have bidded only as per format and the details given by the authorities in bid documents.

Therefore, morally and ethically contractor did wrong but as per law he is entitled to get an change in order and authorities have to issue the same for cost of installing the missing element.


Related Solutions

Assume you are a partner in a successful computer consulting firm bidding for a contract with...
Assume you are a partner in a successful computer consulting firm bidding for a contract with a large insurance company. Your chief rival is a firm that has usually offered services and prices similar to yours. However, from a new employee who used to work for that firm, you learn that it is unveiling a new competitive price structure and accelerated delivery dates, which will undercut the terms you had been prepared to offer the insurance company. Assume you have...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor and the architect? Explain. On a construction project, who ultimately pays for bonds and insurance?
During the construction phase of a health-care project, delays not attributed to the contractor were experienced,...
During the construction phase of a health-care project, delays not attributed to the contractor were experienced, but the contractor was delayed in submitting all delay information required by the contract until 7 days before the contractual completion date, can the architect issue an extension of time prior to the completion date? Explain.
1. What are some advantages and disadvantages of the general contract approach? Assume that the general...
1. What are some advantages and disadvantages of the general contract approach? Assume that the general contact will be awarded on the basis of competitive lump sum bidding. 2. What are the possible options and how a contracting method is selected for a federal-aided highway project?
Nasir, a house painter, and Miguel, a general contractor, met for lunch one day. During lunch,...
Nasir, a house painter, and Miguel, a general contractor, met for lunch one day. During lunch, Nasir and Miguel decided to go into business together, wherein Miguel would send painting referrals to Nasir, Nasir would perform the work and both Nasir and Miguel would split the profits from the business evenly. Miguel has a large net worth and so he was worried about personal liability in the event Nasir caused any damage and was sued. To reassure Miguel, Nasir takes...
During a shift in an environment, general management capability becomes critical to organizational success. Why?
During a shift in an environment, general management capability becomes critical to organizational success. Why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT