Question

In: Accounting

Bob Ross Ltd builds large ships and uses the percentage of completion method of revenue recognition....

Bob Ross Ltd builds large ships and uses the percentage of completion method of revenue recognition. The following information pertains to the construction contracts it had in place as of its December 31, 2012 year-end.

2011

2012

Cost incurred to date

200 million

400 million

Costs to complete contracts

600 million

600 million

Total price of contracts outstanding at December 31, 2012

1,300 million

1,300 million

4a1) How much revenue will Bob's Construction recognize in 2011?

4a2) How much G.P. will Bob's Construction recognizes in 2012?

____________________________________________

4b) Bob Ltd. entered a contract to build a new airport terminal for $2,500,000. Construction commenced on August 1, 2011, with a planned completion date of December 31, 2013. A summary of the costs, billings, and collections is provided below:

2011

2012

2013

Costs incurred during the year

500,000

700,000

1,100,000

Estimated costs to complete at year end

1,500,000

1,200,000

0

Billings during the year

440,000

1,000,000

1,060,000

Cash collections during the year

400,000

900,000

1,200,000

Bob uses the percentage of completion method. What amount would appear as accounts receivable on Bob's December 31, 2012 balance sheet?

____________________________________________

4c) With the same data as 4b, Bob's Construction Ltd. entered a contract to build a new airport terminal for $2,500,000. Construction commenced on August 1, 2011, with a planned completion date of December 31, 2013.  Bob uses the percentage of completion method. How much gross profit would Bob's Construction recognize in 2012?

Solutions

Expert Solution

All amounts are in $

Question 4a)

Assuming that the given "Cost to complete" is total cost and not the estimated further cost.

In 2011, 33.33% of contract is complete (200/600)

In 2012, 66.67% of contract is complete till date (400/600)

4a1)

Revenue recognised in 2011 = 1,800 x 33.33% = 600

4a2)

Revenue to be recognised till 2012 = 1,800 x 66.67% = 1,200

Revenue to be recognised in 2012

= Revenue to be recognised till date - Revenue recognised earlier

= 1,200 - 600

= 600

Gross Profit in 2012 = Revenue recognised in 2012 - Cost incurred in 2012

= 600 - (400-200)

= 400

Question 4b)

Accounts receivable portion must be Billings over Cash receipts

Total Billings in 2011 & 2012 = 1,440,000 (440,000 + 1,000,000)

Total Receipts in 2011 & 2012 = 1,300,000 (400,000 + 900,000)

Accounts Receivable = 1,440,000 - 1,300,000 = 140,000

Question 4c)

Total Costs incurred till date = 500,000 + 700,000 = 1,200,000

Total estimated costs = 1,200,000 + 1,200,000 = 2,400,000

% of completion till end of 2012 = 1,200,000/2,400,000 = 50%

% of completion till end of 2011 = 500,000/(500,000+1,500,000) = 25%

% of revenue to be recognised in 2012 = 50% - 25% = 25%

Revenue recognised in 2012 = 2,500,000 x 25% = 625,000

Costs in 2012 = 700,000

Gross Profit recognised in 2012 = 625,000 - 700,000

= (75,000) (that means a loss of 75,000)


Related Solutions

CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion on the basis of kilometres completed. In November 20X9, CCS signed an agreement with the NWT government to build 50 kilometres of new road for a total cost of $40 million. The contract would likely take three years to complete and would start in the spring of 20X10. Over the next three years, 15 kilometres were completed in 20X10,...
Revenue Recognition - Percentage of Completion - Project Instructions, Spring 2018 One of your clients is...
Revenue Recognition - Percentage of Completion - Project Instructions, Spring 2018 One of your clients is a large regional construction company. The company has many long-term projects in the works. The spreadsheet you are given contains some information about these jobs. Some of the jobs began last year and continue into the current year, so they exist on both tabs. The projects are in various phases of construction; some of which were completed during the current year. You've been asked...
1. Explain Revenue Recognition methods (percentage of completion, completed production, traditional, installment) 2. Explain Expense Recognition...
1. Explain Revenue Recognition methods (percentage of completion, completed production, traditional, installment) 2. Explain Expense Recognition methods (cause & effect, rational & systematic, immediate recognition) 3. Describe Fair value hierarchy: Level 1 - observable (quoted prices), Level 2 (prices of similar items observable), Level 3 (non-observable – must base value on assumptions) 4. Identify the four basic assumptions of accounting: Economic entity, monetary unit, periodicity, and going concern 5. Recognize the two fundamental qualitative characteristics of financial reporting: Relevance and...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
Under which two situations can a firm utilize the percentage completion method to recognize revenue as...
Under which two situations can a firm utilize the percentage completion method to recognize revenue as the asset for sale is being constructed?
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the following should be used in the calculation of the income recognized in the first year? Select one: a. Progress Billings, but not Collections on Progress Billings b. Collections on Progress Billings, but not Progress Billings c. Both Progress Billings and Collections on Progress Billings d. Neither Progress Billings nor Collections on Progress Billings
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost data pertain to this contract for the year-ended 2018... Cost incurred during the year: $7,800,000... Estimated costs to complete: $5,200,000. The following cost data pertain to this contract for the year-ended 2019... Cost incurred during the year: $5,600,000... Estimated costs to complete: n/a. If the completed-contract method of accounting was used, the amount of gross...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an apartment complex for Dan for $30mn. Mann estimates that total costs would amount to $22mn over the period of construction. In connection with this contract, Mann incurs $3mn of construction costs during 20X5. Mann bills and collects $4mn from Dan in 20X5. What amount should Mann recognize as gross profit for 20X5? A. $4,000,000 B. $3,000,000 C. $1,000,000 D. $1,090,909 Fam Construction Company's contract...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT