Question

In: Accounting

Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...

Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow:

2020 2021

Costs incurred during the year

$706,640 $1,422,000

Estimated costs to complete, as at December 31

899,360 0

Billings during the year (non-refundable)

420,000 1,713,600

Collections during the year

352,000 1,481,000

How much revenue should be recognized in 2020 and in 2021?

2020 2021

Revenue to be recognized

$enter a dollar amount $enter a dollar amount

Assuming the same facts as those above except that Cullumber uses the completed-contract method of accounting, how much revenue should be recognized in 2021?

2021

Revenue to be recognized

$enter a dollar amount

  

  

Prepare a complete set of journal entries for 2020. (using the percentage-of-completion method. Use Materials, Cash, Payables for costs incurred to date.) (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

(To record cost of construction)

enter an account title to record progress billings

enter a debit amount

enter a credit amount

enter an account title to record progress billings

enter a debit amount

enter a credit amount

(To record progress billings)

enter an account title to record collections

enter a debit amount

enter a credit amount

enter an account title to record collections

enter a debit amount

enter a credit amount

(To record collections)

enter an account title to record revenues

enter a debit amount

enter a credit amount

enter an account title to record revenues

enter a debit amount

enter a credit amount

(To record revenues)

enter an account title to record construction expenses

enter a debit amount

enter a credit amount

enter an account title to record construction expenses

enter a debit amount

enter a credit amount

(To record construction expenses)

Solutions

Expert Solution

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Cullumber Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
2020 $706,640 $706,640 $1,606,000 44.00% $2,178,000 $958,320 $958,320 $251,680
2021 $1,422,000 $2,128,640 $2,128,640 100.00% $2,178,000 $2,178,000 $1,219,680 -$202,320

revenue should be recognized in 2021 using completed contract method = $2,178,000

Journal Entries - Cullumber Construction Company - 2020
Event Particulars Debit Credit
1 Construction in Progress Dr $706,640.00
       To Materials, cash, payables $706,640.00
(To record construction cost incurred)
2 Accounts receivables Dr $420,000.00
       To Billings on construction contract $420,000.00
(To record progress billings)
3 Cash Dr $352,000.00
       To Accounts receivables $352,000.00
(To record collection from customer)
4 Construction in Progress Dr $706,640.00
Cost of construction Dr $251,680.00
       To Revenue from long term contracts $958,320.00
(To record revenue and gross profit)

Related Solutions

Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost data pertain to this contract for the year-ended 2018... Cost incurred during the year: $7,800,000... Estimated costs to complete: $5,200,000. The following cost data pertain to this contract for the year-ended 2019... Cost incurred during the year: $5,600,000... Estimated costs to complete: n/a. If the completed-contract method of accounting was used, the amount of gross...
(Analysis of Percentage-of-Completion Financial Statements) In 2020, Steinrotter Construction Corp. began construction work under a 3-year...
(Analysis of Percentage-of-Completion Financial Statements) In 2020, Steinrotter Construction Corp. began construction work under a 3-year contract. The contract price was $1,000,000. Steinrotter uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2020, are shown below. Balance Sheet Accounts receivable $18,000 Construction in process $65,000 Less: Billings...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
In the construction industry, the percentage of completion (POC) method is the most common accounting method....
In the construction industry, the percentage of completion (POC) method is the most common accounting method. Explain what business environments create favorable conditions for a company to use this POC method.
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the following should be used in the calculation of the income recognized in the first year? Select one: a. Progress Billings, but not Collections on Progress Billings b. Collections on Progress Billings, but not Progress Billings c. Both Progress Billings and Collections on Progress Billings d. Neither Progress Billings nor Collections on Progress Billings
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an apartment complex for Dan for $30mn. Mann estimates that total costs would amount to $22mn over the period of construction. In connection with this contract, Mann incurs $3mn of construction costs during 20X5. Mann bills and collects $4mn from Dan in 20X5. What amount should Mann recognize as gross profit for 20X5? A. $4,000,000 B. $3,000,000 C. $1,000,000 D. $1,090,909 Fam Construction Company's contract...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion on the basis of kilometres completed. In November 20X9, CCS signed an agreement with the NWT government to build 50 kilometres of new road for a total cost of $40 million. The contract would likely take three years to complete and would start in the spring of 20X10. Over the next three years, 15 kilometres were completed in 20X10,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT