Question

In: Accounting

Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...

Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts.....

They were working on a contract for which they would receive $900,000 at completion....

In 2024, they reported a gross profit of 58,440.....

2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266 to finish the project.

How much of a loss should they report in 2025? (Enter the loss as a positive number...Example: loss of "150,000".)

Solutions

Expert Solution

The percentage-of-completion method attempts to recognize revenues and gross profit in the applicable periods of construction, and not soley in the period when the construction has been completed, as in the completed contract method. The degree of completion of the construction, i.e., the percentage-of-completion, is typically estimated by dividing the total construction costs incurred to date by the total estimated costs of the contract, or job.

Recognition of expected losses - When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.

The amount of such a loss is determined irrespective of: (a) whether or not work has commenced on the contract; (b) the stage of completion of contract activity; or (c) the amount of profits expected to arise on other contracts which are not treated as a single construction contract..

we are aware that this project is going to incurr the losses due to the disasterous 2025 year

Lets calculate the total cost incurred and total cost will be incurred in future.

A. Total cost incurred in 2024 and 2025 = $800,000

B. Expected cost to be incurred to finish the project =  $120,266

C.Total cost incurred and to be incurred for the project = A + B = 800,000 + 120,266 = $ 920,266

D. Total revenue revenue = $ 900,00

Total loss to be recognised in 2025 =   Total Revenue (D) - Total cost incurred (A)- Total cost expected to be incurred (B)

=$ 900,000-800,000-120,266

= -$20,266

Hence the Madoff Construction Company should report loss of $ 20,266 in 2025

Note -  Gross profit of 58,440 in 2024 has been given in question just to confuse the student. You should ignore it in this question and solve question based on recognition of expected losses principle mentioned above.


Related Solutions

Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the following should be used in the calculation of the income recognized in the first year? Select one: a. Progress Billings, but not Collections on Progress Billings b. Collections on Progress Billings, but not Progress Billings c. Both Progress Billings and Collections on Progress Billings d. Neither Progress Billings nor Collections on Progress Billings
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has...
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has a contract price of $130,000,000 with total estimated costs of $100,000,000. AttiK appropriately uses the percentage of completion method. After 2 years of construction, the following costs have been accumulated: Actual cost incurred, Year 1 $30,000,000 Total estimated costs remaining after Year 1 70,000,000 Actual cost incurred, Year 2 50,000,000 Total estimated cost remaining after Year 2 20,000,000 Determine the gross profit for each...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion on the basis of kilometres completed. In November 20X9, CCS signed an agreement with the NWT government to build 50 kilometres of new road for a total cost of $40 million. The contract would likely take three years to complete and would start in the spring of 20X10. Over the next three years, 15 kilometres were completed in 20X10,...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
During 2019, ABC Construction company changed from the cost-recovery method to the percentage-of-completion method for accounting...
During 2019, ABC Construction company changed from the cost-recovery method to the percentage-of-completion method for accounting purposes but not for tax purposes. Gross profit figures under both methods for the past three years appear below:                            Cost-Recovery           Percentage-of-Completion 2017                      $   475,000                        $   900,000 2018                           625,000 1,050,000 2019                           700,000     1,050,000                               $1,800,000 $3,000,000 Assuming an income tax rate of 40% for all years. the effect of this accounting change on prior periods should be reported by a credit of........... Select one: a. $510,000...
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method....
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method. It is a 4 year contract that is currently in its second year. The latest estimates of contact costs indicate that the contact will be completed at a profit to the company. Based on this information please answer the following: 1 What theoretical justification is there or the Widjaja Company's use of the percentage-of-completion method 2 Discuss how the progress billings will be accounted...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost data pertain to this contract for the year-ended 2018... Cost incurred during the year: $7,800,000... Estimated costs to complete: $5,200,000. The following cost data pertain to this contract for the year-ended 2019... Cost incurred during the year: $5,600,000... Estimated costs to complete: n/a. If the completed-contract method of accounting was used, the amount of gross...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an apartment complex for Dan for $30mn. Mann estimates that total costs would amount to $22mn over the period of construction. In connection with this contract, Mann incurs $3mn of construction costs during 20X5. Mann bills and collects $4mn from Dan in 20X5. What amount should Mann recognize as gross profit for 20X5? A. $4,000,000 B. $3,000,000 C. $1,000,000 D. $1,090,909 Fam Construction Company's contract...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT