Question

In: Accounting

Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...

Horner Construction Co. uses the percentage-of-completion

method. In 2018, Horner began work on a contract for

$22,000,000; it was completed in 2019. The following cost data

pertain to this contract for the year-ended 2018... Cost incurred

during the year: $7,800,000... Estimated costs to complete:

$5,200,000. The following cost data pertain to this contract for the

year-ended 2019... Cost incurred during the year: $5,600,000...

Estimated costs to complete: n/a. If the completed-contract method

of accounting was used, the amount of gross profit (loss)to be

recognized for years 2018 and 2019 would be

a. 2018: $9,000,000... 2019: $ 0

b. 2018: $8,600,000... 2019: ($400,000)

c. 2018: $ 0... 2019: $8,600,000

d. 2018: $ 0... 2019: $9,000,000

Solutions

Expert Solution

The completed-contract method recognise the profit or loss only on completion of the project. Hence in the year 2018 no profit or loss will be recognised as the project is not completed. In the year 2019, project is completed, profit or loss to be recognised:

                                     Price of the Contract = 22,000,000

Less: cost incurred (7,800,000 + 5,600,000) = 13,400,000

                                                            Profit = 8,600,000

So, the option c is right.


Related Solutions

Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the...
A company uses the percentage-of-completion method to account for a 4-year construction contract. Which of the following should be used in the calculation of the income recognized in the first year? Select one: a. Progress Billings, but not Collections on Progress Billings b. Collections on Progress Billings, but not Progress Billings c. Both Progress Billings and Collections on Progress Billings d. Neither Progress Billings nor Collections on Progress Billings
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which began on January 1, 2015 to build a new football stadium with an expected completion date of October 31, 2017. The following table provides information gathered during the construction period. Jim uses the percentage completion method to account for this contract.                                                                                                                                  2015 2016 2017 Construction costs incurred during the year 2,040,000 2,932,500 1,657,500 Estimated costs to complete 3,060,000 1,657,500 0 Billings during the...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an...
Mann Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mann contracts to build an apartment complex for Dan for $30mn. Mann estimates that total costs would amount to $22mn over the period of construction. In connection with this contract, Mann incurs $3mn of construction costs during 20X5. Mann bills and collects $4mn from Dan in 20X5. What amount should Mann recognize as gross profit for 20X5? A. $4,000,000 B. $3,000,000 C. $1,000,000 D. $1,090,909 Fam Construction Company's contract...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method?...
When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method? I am trying to calculate the revenue. I have information about the estimated cost, cost incurred per year, the finalized cost, project years, and margin. However, I am not sure it is necessary. It said that the worker wants to add a margin of % on its cost estimate. Can anyone help me to use an example to explain to me?
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method....
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method. It is a 4 year contract that is currently in its second year. The latest estimates of contact costs indicate that the contact will be completed at a profit to the company. Based on this information please answer the following: 1 What theoretical justification is there or the Widjaja Company's use of the percentage-of-completion method 2 Discuss how the progress billings will be accounted...
Ex. 18-134—Percentage-of-completion method. Penner Builders contracted to build a high-rise for €35,000,000. Construction began in 2018...
Ex. 18-134—Percentage-of-completion method. Penner Builders contracted to build a high-rise for €35,000,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are:    2018 2019 costs incurred to date    4.5M 13M Estimated cost to complete 18M. 12M Penner uses the percentage-of-completion method. Instructions A: How much gross profit should be reported for 2018? Show your computation. B: How much gross profit should be reported for 2019? C: Make the journal Entry...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT