In: Accounting
Pinetree Builders has the following data for its Rolling Hills Construction Project. The contract price of the project is $18,000,000. Complete the following table with the required information using the percentage of completion method.
2016 |
2017 |
2018 |
|
Costs incurred to date |
$4,500,000 |
$10,500,000 |
$15,500,000 |
Estimated costs to complete |
10,500,000 |
2,625,000 |
|
Billings during the year |
6,600,000 |
8,400,000 |
3,000,000 |
Cash collections during the year |
6,000,000 |
6,000,000 |
6,000,000 |
Estimated total costs |
|||
Estimated total profit |
|||
Percentage of Completion |
|||
Revenue Recognized in each year |
|||
Profit recognized in each year |
|||
Current Asset |
|||
Current Liabilities |
Required
1. Enter the appropriate amounts in the shaded cells above.
2. Prepare the required journal entries for 2016, 2017 and 2018.
Date |
Accounts Title and Explanation |
Ref. |
Debit |
Credit |
2016 | 2017 | 2018 | |||||
a | Costs incurred to date | $4,500,000 | $10,500,000 | $15,500,000 | |||
b | Estimated costs to complete | 10,500,000 | 2,625,000 | 0 | |||
c | Billings during the year | 6,600,000 | 8,400,000 | 3,000,000 | |||
d | Cash collections during the year | 6,000,000 | 6,000,000 | 6,000,000 | |||
e=a+b | Estimated total costs | $15,000,000 | (4500000+10500000) | $13,125,000 | (10500000+2625000) | $15,500,000 | (15500000+0) |
f=Total contract revenue-e | Estimated total profit | $3,000,000 | (18000000-15000000) | $4,875,000 | (18000000-13125000) | $2,500,000 | (18000000-15500000) |
g=a/e*100 | Percentage of Completion | 30% | (4500000/15000000)*100 | 80% | (10500000/13125000)*100 | 100% | (15500000/15500000)*100 |
h=total contract revenue*% increase in completion | Revenue Recognized in each year | 5400000 | (18000000*30%) | 9000000 | (18000000*(80%-30%)) | 3600000 | (18000000*(100%-80%)) |
i=(f*g)-profit recognised till date | Profit recognized in each year | $900,000 | (3000000*30%)-0 | $3,000,000 | (4875000*80%)-900000 | ($1,400,000) | (2500000*100%)-(900000+3000000) |
j=refer working note | Current Asset | 6,600,000 | 15,000,000 | 18,000,000 | |||
k=a | Current Liabilities | $5,700,000 | $11,100,000 | $15,500,000 | |||
Current assets | |||||||
Cash | 6,000,000 | 12,000,000 | (6000000+6000000) | 18,000,000 | (6000000+12000000) | ||
(opening trade receivable+Billing done during the year-cash collection during the year) | Trade Receivable | 600,000 | (0+6600000-6000000) | 3,000,000 | (600000+8400000-6000000) | 0 | (3000000+3000000-6000000) |
(Revenue recognised till date-billing done till date) | Amount due from customer | 6,600,000 | 15,000,000 | 18,000,000 | |||
Total | |||||||
Current liability | |||||||
(billing done till date-revenue recognisedtill date) | Amount due to customer | 1,200,000 | $600,000 | 0 | (18000000-18000000) | ||
k=a | Trade payable | $4,500,000 | $10,500,000 | $15,500,000 | |||
5,700,000 | $11,100,000 | 15500000 | |||||
Year1 | |||||||
1 | Construction in Progress | $4,500,000 | |||||
Trade Payable | $4,500,000 | ||||||
2 | Accounts Receiavble | 6,600,000 | |||||
Billing on construction Contract | 6,600,000 | ||||||
3 | Cash | 6,000,000 | |||||
Trade Receivable | 6,000,000 | ||||||
4 | Construction in progress | $900,000 | |||||
Construction Expense | $4,500,000 | ||||||
Construction Revenue | 5400000 | ||||||
5 | Billing on construction Contract | 1,200,000 | |||||
Amount due to customer | 1,200,000 | ||||||
Year2 | |||||||
1 | Construction in Progress | $6,000,000 | (10500000-4500000) | cost incurred during year | |||
Trade Payable | $6,000,000 | ||||||
2 | Accounts Receiavble | 8,400,000 | |||||
Billing on construction Contract | 8,400,000 | ||||||
3 | Cash | 6,000,000 | |||||
Trade Receivable | 6,000,000 | ||||||
4 | Construction in progress | $3,000,000 | |||||
Construction Expense | 6,000,000 | ||||||
Construction Revenue | 9000000 | ||||||
5 | Billing on construction Contract | 600,000 | |||||
Amount due to customer | 600,000 | ||||||
Year3 | |||||||
1 | Construction in Progress | $15,500,000 | |||||
Trade Payable | $15,500,000 | ||||||
2 | Accounts Receiavble | 3,000,000 | |||||
Billing on construction Contract | 3,000,000 | ||||||
3 | Cash | 6,000,000 | |||||
Trade Receivable | 6,000,000 | ||||||
4 | Construction Expense | $5,000,000 | |||||
Construction Revenue | 3600000 | ||||||
Construction in progress | $1,400,000 |