Question

In: Accounting

Pinetree Builders has the following data for its Rolling Hills Construction Project. The contract price of...

Pinetree Builders has the following data for its Rolling Hills Construction Project. The contract price of the project is $18,000,000. Complete the following table with the required information using the percentage of completion method.

2016

2017

2018

Costs incurred to date

$4,500,000

$10,500,000

$15,500,000

Estimated costs to complete

10,500,000

2,625,000

Billings during the year

6,600,000

8,400,000

3,000,000

Cash collections during the year

6,000,000

6,000,000

6,000,000

Estimated total costs

Estimated total profit

Percentage of Completion

Revenue Recognized in each year

Profit recognized in each year

Current Asset

Current Liabilities

Required

1.         Enter the appropriate amounts in the shaded cells above.

2.         Prepare the required journal entries for 2016, 2017 and 2018.

Date

Accounts Title and Explanation

Ref.

Debit

Credit

Solutions

Expert Solution

2016 2017 2018
a Costs incurred to date $4,500,000 $10,500,000 $15,500,000
b Estimated costs to complete 10,500,000 2,625,000 0
c Billings during the year 6,600,000 8,400,000 3,000,000
d Cash collections during the year 6,000,000 6,000,000 6,000,000
e=a+b Estimated total costs $15,000,000 (4500000+10500000) $13,125,000 (10500000+2625000) $15,500,000 (15500000+0)
f=Total contract revenue-e Estimated total profit $3,000,000 (18000000-15000000) $4,875,000 (18000000-13125000) $2,500,000 (18000000-15500000)
g=a/e*100 Percentage of Completion 30% (4500000/15000000)*100 80% (10500000/13125000)*100 100% (15500000/15500000)*100
h=total contract revenue*% increase in completion Revenue Recognized in each year 5400000 (18000000*30%) 9000000 (18000000*(80%-30%)) 3600000 (18000000*(100%-80%))
i=(f*g)-profit recognised till date Profit recognized in each year $900,000 (3000000*30%)-0 $3,000,000 (4875000*80%)-900000 ($1,400,000) (2500000*100%)-(900000+3000000)
j=refer working note Current Asset 6,600,000 15,000,000 18,000,000
k=a Current Liabilities $5,700,000 $11,100,000 $15,500,000
Current assets
Cash 6,000,000 12,000,000 (6000000+6000000) 18,000,000 (6000000+12000000)
(opening trade receivable+Billing done during the year-cash collection during the year) Trade Receivable 600,000 (0+6600000-6000000) 3,000,000 (600000+8400000-6000000) 0 (3000000+3000000-6000000)
(Revenue recognised till date-billing done till date) Amount due from customer 6,600,000 15,000,000 18,000,000
Total
Current liability
(billing done till date-revenue recognisedtill date) Amount due to customer 1,200,000 $600,000 0 (18000000-18000000)
k=a Trade payable $4,500,000 $10,500,000 $15,500,000
5,700,000 $11,100,000 15500000
Year1
1 Construction in Progress $4,500,000
Trade Payable $4,500,000
2 Accounts Receiavble 6,600,000
Billing on construction Contract 6,600,000
3 Cash 6,000,000
Trade Receivable 6,000,000
4 Construction in progress $900,000
Construction Expense $4,500,000
Construction Revenue 5400000
5 Billing on construction Contract 1,200,000
Amount due to customer 1,200,000
Year2
1 Construction in Progress $6,000,000 (10500000-4500000) cost incurred during year
Trade Payable $6,000,000
2 Accounts Receiavble 8,400,000
Billing on construction Contract 8,400,000
3 Cash 6,000,000
Trade Receivable 6,000,000
4 Construction in progress $3,000,000
Construction Expense 6,000,000
Construction Revenue 9000000
5 Billing on construction Contract 600,000
Amount due to customer 600,000
Year3
1 Construction in Progress $15,500,000
Trade Payable $15,500,000
2 Accounts Receiavble 3,000,000
Billing on construction Contract 3,000,000
3 Cash 6,000,000
Trade Receivable 6,000,000
4 Construction Expense $5,000,000
Construction Revenue 3600000
Construction in progress $1,400,000

Related Solutions

Action Steel entered into a contract with Systems Builders for the construction of an addition to...
Action Steel entered into a contract with Systems Builders for the construction of an addition to a commercial building. Systems Builders was the general contractor and agreed to erect a building designed and manufactured by Varco-Pruden. Part of Systems Builders’ contract with Action Steel included an agreement for the parties not to sue each other or any subcontractors or agents if another insurance plan was taken out on neighboring properties or the finished project. During the first winter after construction...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to be received when the project is completed in 2018. During 2016, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2017, Indiana incurred additional costs of $63.75 million...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
ABC Construction has the following contract: Contract price 1,000,000 Cost incurred cost to complete Dec 31...
ABC Construction has the following contract: Contract price 1,000,000 Cost incurred cost to complete Dec 31 2017 200,000 600,000 Dec 31 2018 350,000 250,000 Dec 31 2019 300,000 850,000 Billings Cash Received Dec 31 2017 250,000 200,000 Dec 31 2018 400,000 350,000 Dec 31 2019 350,000 450,000 1,000,000 1,000,000 A. Prepare a % of completion schedule for the three years B. Prepare journal entries for 3 years
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT