The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. They work a 7 hour day and want to produce at a rate of 360 units per day. What should their cycle time be?

Task Time (sec) Predecessor

A 45 --

B 50 A

C 40 A

D 55 B, C

E 40 D

F 65 D

G 25 E

H 35 F, G

Options

A: 52 seconds

B: 25 seconds

C: 70 seconds

D: 80 seconds

Solutions

Expert Solution

Answer - (C) 70 seconds
Explanation - Cycle time = Average time between completion of units

If for 360 units, 7 hours are required in a day,
Therefore for 1 unit, average throughput rate = 7/360 = 1.167 minutes
Hence, cycle time = 70 seconds (1.167 * 60) on average.


Related Solutions

List and define the three basic goals of a design team for the design of any...
List and define the three basic goals of a design team for the design of any building. Provide an example of each of the following types of construction. Bearing wall a. Beam-and-column b. Long-span c. High-rise d. Gable-frame List and describe two types of lateral load resisting systems commonly used in beam-andcolumn construction. Provide a simple definition of structural design. Give a description of both the LRFD and ASD design approaches. What is the fundamental difference between the methods? Identify...
Whack Ltd, a tennis racquet manufacturer, has broken the production process into three lines, each in...
Whack Ltd, a tennis racquet manufacturer, has broken the production process into three lines, each in a different department: framing, stringing, and finishing. The following information relates to each department for the month of April:                              FRAMING STRINGING FINISHING Direct Costs       $20,000      $30,000         $66,000 Indirect Costs $10,000      $20,000         $30,000 Labour Hours   2,000 hrs   5,000 hrs      3,000 hrs Machine hours 500 hrs      0 hrs            0 hrs Production for April is 10,000 racquets Refer to the table above. The overhead recovery rate for stringing...
Briefly explain the steps of team building process
Briefly explain the steps of team building process
List eight characteristics of services and explain what impact each characteristic has on the design process.
List eight characteristics of services and explain what impact each characteristic has on the design process.
‏Decision making can be viewed as an eight - step process , use these steps in...
‏Decision making can be viewed as an eight - step process , use these steps in making any decision . Please use your own example and do not take the examples from the PowerPoint presentation ( buying a car or a computer ) ?
What are the steps of design process in architecture and explain each one?
What are the steps of design process in architecture and explain each one?
Discuss the basic steps in the recording process, using the transaction of Wong Ltd for the...
Discuss the basic steps in the recording process, using the transaction of Wong Ltd for the month ended 31 October (attached). Your discussion and presentation should include the following: a) Analysis each transaction in terms of its effect on the accounts. b) Recording of each transaction information in a journal. c) Transferring (posting) the journal information to the appropriate accounts in the ledger. d) Preparation of a trial balance (from account balances in the general ledger). Wong Pty Ltd The...
What are basic characteristics of a self-organization team and steps to become self-organized? (from an agile...
What are basic characteristics of a self-organization team and steps to become self-organized? (from an agile methodology point of view)
What are the three basic steps in the programming of Polymerase Chain Reaction (PCR) process?
What are the three basic steps in the programming of Polymerase Chain Reaction (PCR) process?
A manufacturer has two production departments: Assembly; Finishing. In Assembly, the budget MOH rate is $10...
A manufacturer has two production departments: Assembly; Finishing. In Assembly, the budget MOH rate is $10 per machine hour. In Finishing, the budget rate is 150% of direct labor dollars. Company records indicate the following information about Job A: Assembly Finishing 20,000 4,000 DM (in $) 5,000 15,000 DL (in $) 400 100 machine hours Calculate the total cost of Job A according to GAAP. a. 44,000 b. 48,000 c. 49,000 d. 70,500 e. 79,000
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT