Question

In: Accounting

Assume that manufacturing overhead for Windsor Company consisted of the following activities and costs: Setup (1,000...

Assume that manufacturing overhead for Windsor Company consisted of the following activities and costs:

Setup (1,000 setup hours) $ 92,000
Production scheduling (300 batches) 24,000
Production engineering (70 change orders) 70,000
Supervision (2,200 direct labor hours) 66,000
Machine maintenance (13,000 machine hours) 78,000
Total activity costs $ 330,000


The following additional data were provided for Job 845:

Direct material costs $ 6,000
Direct labor cost (5 Milling direct labor hours; 25 Finishing direct labor hours) $ 1,000
Setup hours 5 hours
Production scheduling 1 batch
Machine hours used (15 Milling machine hours; 5 Finishing machine hours) 20 hours
Production engineering 2 change orders


(a) Calculate the cost per unit of activity driver for each activity cost category.

Setup $Answer
Production scheduling $Answer
Production engineering $Answer
Supervision $Answer
Machine operating $Answer


(b) Calculate the cost of Job 845 using ABC to assign the overhead costs.
$Answer



(c) Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours of $30 per hour. (Round your answer to the nearest dollar.)
$Answer



(d) Calculate the cost of Job 845 using a machine hour departmental overhead rate for the Milling Department ($26 per hour) and a direct hour overhead rate for the Finishing Department ($96 per hour). (Round your answer to the nearest dollar.)  
$Answer

Solutions

Expert Solution

The answer has been presented in the supporting sheet . All the parts has been solved with detailed explanation and calculation. For detailed answer refer to the supporting sheet.


Related Solutions

Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000...
Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000 The following additional data were provided for Job 845: Direct material costs $ 8,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours) $ 1,000 Setup hours 5...
Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000...
Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $168,000 Production scheduling (400 batches) 50,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 64,000 Machine maintenance (12,000 machine hours) 108,000 Total activity costs $540,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5 hours Production scheduling 1 batch...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 30,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 64,000 Machine maintenance (12,000 machine hours) 84,000 Total activity costs $386,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $150,000 Production scheduling (400 batches) 80,000 Production engineering (60 change orders) 60,000 Supervision (2,000 direct labor hours) 66,000 Machine maintenance (12,000 machine hours) 48,000 Total activity costs $404,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $150,000 Production scheduling (400 batches) 80,000 Production engineering (60 change orders) 60,000 Supervision (2,000 direct labor hours) 66,000 Machine maintenance (12,000 machine hours) 48,000 Total activity costs $404,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead...
Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead $187,200 Finishing Department manufacturing overhead $76,800 Machine hours used Milling Department 9,000 hours Finishing Department 2,000 hours Labor hours used Milling Department 1,000 hours Finishing Department 1,000 hours Required a. Calculate the plantwide manufacturing overhead rate using machine hours as the allocation base. $Answer per machine hour b. Calculate the plantwide manufacturing overhead rate using direct labor hours as the allocation base. $Answer per...
Windsor Company was incorporated on January 2, 2018, but was unable to begin manufacturing activities until...
Windsor Company was incorporated on January 2, 2018, but was unable to begin manufacturing activities until July 1, 2018, because new factory facilities were not completed until that date. The Land and Buildings account reported the following items during 2018. January 31 Land and building $165,900 February 28 Cost of removal of building 9,973 May 1 Partial payment of new construction 63,430 May 1 Legal fees paid 4,630 June 1 Second payment on new construction 48,600 June 1 Insurance premium...
Assume a product has the following activities and overhead costs: Production ($40 per labor hour) Assembly...
Assume a product has the following activities and overhead costs: Production ($40 per labor hour) Assembly ($25 per labor hour) Quality Inspection ($100 per inspection) Also assume that each product requires 5 hours of direct labor hours for production, 4 hours of direct labor hours for assembly, and one inspection for every 10 units produced. If the company produces 100 units, what is the total overhead cost?
Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs,...
Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $466,260 Number of setups 570 Ordering costs 369,600 Number of orders 17,600 Machine costs 702,100 Machine hours 41,300 Receiving 414,000 Receiving hours 9,200 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $574,000 $790,000 Direct...
DAB Company has identified the following overhead activities, costs, and activity drivers for the coming year:...
DAB Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity                                Expected Cost          Activity Driver               Activity Capacity Material-handling costs.. £45,000             Number of moves.........        450 Machine costs................ £80,000             Machine hours.............. 20,000 Order costs.................... £15,000             Number of orders.........        750 Receiving costs.............. £30,000             Number of parts........... 50,000 Setup costs.................... £50,000             Number of setups.........        250 Assume that each activity corresponds to a process. DAB’s normal activity is 5,000 direct labor hours. The following two jobs...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT