In: Accounting
Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs:
Setup (1,000 setup hours) | $ 146,000 |
Production scheduling (400 batches) | 60,000 |
Production engineering (60 change orders) | 90,000 |
Supervision (2,000 direct labor hours) | 56,000 |
Machine maintenance (12,000 machine hours) | 96,000 |
Total activity costs | $ 448,000 |
The following additional data were provided for Job 845:
Direct material costs | $ 8,000 |
Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours) | $ 1,000 |
Setup hours | 5 hours |
Production scheduling | 1 batch |
Machine hours used (25 Milling machine hours;5 Finishing machine hours) | 30 hours |
Production engineering | 3 change orders |
(a) Calculate the cost per unit of activity driver for each
activity cost category.
Setup | Answer |
Production scheduling | Answer |
Production engineering | Answer |
Supervision | Answer |
Machine operating | Answer |
(b) Calculate the cost of Job 845 using ABC to assign the overhead
costs.
$Answer
(c) Calculate the cost of Job 845 using the plantwide overhead rate
based on machine hours. (Round your answer to the nearest
dollar.)
$Answer
(d) Calculate the cost of Job 845 using a machine hour departmental
overhead rate for the Milling Department ($28 per hour) and a
direct hour overhead rate for the Finishing Department ($100 per
hour). (Round your answer to the nearest dollar.)
$Answer
Answer to Question a:
Answer to Question b:
Activity Cost = Activity Rate X Activity Consumed
Answer to Question c and d: