In: Accounting
Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs:
|
Setup (1,000 setup hours) |
$168,000 |
|
Production scheduling (400 batches) |
50,000 |
|
Production engineering (60 change orders) |
150,000 |
|
Supervision (2,000 direct labor hours) |
64,000 |
|
Machine maintenance (12,000 machine hours) |
108,000 |
|
Total activity costs |
$540,000 |
The following additional data were provided for Job 845:
|
Direct materials costs |
$7,000 |
|
Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) |
$1,000 |
|
Setup hours |
5 hours |
|
Production scheduling |
1 batch |
|
Machine hours used (25 Milling machine hours;5 Finishing machine hours) |
30 hours |
|
Production engineering |
3 change orders |
(b) Calculate the cost of Job 845 using ABC to assign the
overhead costs.
$Answer
(c) Calculate the cost of Job 845 using the plantwide overhead rate
based on machine hours. (Round your answer to the nearest
dollar.)
$Answer
(d) Calculate the cost of Job 845 using a machine hour departmental
overhead rate for the Milling Department ($42 per hour) and a
direct hour overhead rate for the Finishing Department ($108 per
hour). (Round your answer to the nearest dollar.)
$Answer
| Activity | Cost | Cost Driver | Quantity | Cost per cost driver |
| Setup | $ 168,000.00 | Setup hours | 1000 | $ 168.00 |
| Production scheduling | $ 50,000.00 | batches | 400 | $ 125.00 |
| Production engineering | $ 150,000.00 | change orders | 60 | $ 2,500.00 |
| Supervision | $ 64,000.00 | direct labor hours | 2000 | $ 32.00 |
| Machine Maintenance | $ 108,000.00 | machine hours | 12000 | $ 9.00 |
| Total | $ 540,000.00 |
b.
| Job 845 | ||
| Overhead allocated | ||
| Setup | $ 840.00 | =5*168 |
| Production scheduling | $ 125.00 | =1*125 |
| Production engineering | $ 7,500.00 | =3*2500 |
| Supervision | $ 1,280.00 | =40*32 |
| Machine Maintenance | $ 270.00 | =30*9 |
| Total Manufacturing Overhead | $ 10,015.00 | |
| Direct Material | $ 7,000.00 | |
| Direct Labor | $ 1,000.00 | |
| Total Cost | $ 18,015.00 |
c. Plantwide overhead rate = $540000/12000 = $45 per machine hour
| Job 845 | |
| Total Manufacturing Overhead | $ 1,350.00 |
| Direct Material | $ 7,000.00 |
| Direct Labor | $ 1,000.00 |
| Total Cost | $ 9,350.00 |
d.
| Job 845 | ||
| Overhead allocated | ||
| Milling Department | $ 1,050.00 | =25*42 |
| Finishing Department | $ 3,780.00 | =35*108 |
| Total Manufacturing Overhead | $ 4,830.00 | |
| Direct Material | $ 7,000.00 | |
| Direct Labor | $ 1,000.00 | |
| Total Cost | $ 12,830.00 |