In: Operations Management
DAB Company has identified the following overhead activities, costs, and activity drivers for the coming year:
Activity Expected Cost Activity Driver Activity Capacity
Material-handling costs.. £45,000 Number of moves......... 450
Machine costs................ £80,000 Machine hours.............. 20,000
Order costs.................... £15,000 Number of orders......... 750
Receiving costs.............. £30,000 Number of parts........... 50,000
Setup costs.................... £50,000 Number of setups......... 250
Assume that each activity corresponds to a process. DAB’s normal activity is 5,000 direct labor hours. The following two jobs were completed during March:
Job X-1 Job Y-4
Direct materials.......................... £1,500 £2,000
Direct labor (£15 per hour)......... £750 £750
Units completed.......................... 200 200
Number of moves........................ 3 6
Machine hours............................ 125 75
Number of orders........................ 3 12
Number of parts.......................... 200 800
Number of setups....................... 1 4
Required:
Determine the unit cost for each job using direct labor hours to apply overhead.
Determine the unit cost for each job using the activity drivers to apply overhead.
Which method produces the more accurate cost assignment? Why?
(8 Marks)
Using direcr labor hours
Job X-1 Job Y-4
Direct Materials 1500 2000
Direct Labor 750 750
Overhead cost= 44*50=2200 2200
(Total Overhead cost/ Total labor hours)*labour hours used
Total cost= 4450 4950
Unit cost= 4450/200=22.25 4950/200= 24.75
b- According to activity driver
Job X-1 | Job Y-4 | |
Direct Materials | 1500 | 2000 |
Direct Labors | 750 | 750 |
Material Handing Cost 45000/450= 100 |
100*3= 300 | 100*6= 600 |
Machine Costs 80,000/20,000= 4 |
4*125= 500 | 4*75= 150 |
Orders Cost 150,000/750= 200 |
200*3= 600 | 200*12= 2400 |
Receiving Cost 30,000/50,000=0.6 |
0.6*200=120 | 0.6*800=480 |
Setup Cost 50,000/250=200 |
200*1= 200 | 200*4= 800 |
Total cost | 3970 | 7180 |
Units produced | 200 | 200 |
Unit cost | 3970/200=19.85 | 7180/200=35.9 |
Second method i.e.unit cost for each job using the activity drivers to apply overhead provide accurate cost assignment because in this method cost is assigned as per use not in generalized.