In: Finance
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a. If the required return is 19 percent, what is the NPV for this project? b. Determine the IRR for this project.
| Ans 1 | computation of NPV | |||||||
| We have to use the financial calculator to solve for the present value of cash inflow | ||||||||
| put in calculator | ||||||||
| FV | 0 | |||||||
| PMT | -10500 | |||||||
| I | 19% | |||||||
| N | 8 | |||||||
| Compute PV | $41,520.84 | |||||||
| i | Present value of cash inflow = | $ 41,520.84 | ||||||
| ii | Present value of cash outflow = | $ 50,387.00 | ||||||
| iii=i-ii | NPV= | ($8,866.16) | ||||||
| Ans = | ($8,866.16) | |||||||
| Ans 2 | We have to use financial calculator to solve for IRR | |||||||
| Put in calculator | ||||||||
| FV | 0 | |||||||
| PV | -50387 | |||||||
| PMT | 10500 | |||||||
| N | 8 | |||||||
| Compute I | 13.00% | |||||||
| IRR = | 13.00% | |||||||