Question

In: Finance

A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A)...

A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today.

A) If the required return is 4 percent, what is the NPV for this project?

B)Determine the IRR for this project.

Solutions

Expert Solution

a) NPV = -Initial investment + Present value of cash flows

NPV = -$81,395 + $14,700/1.04 + $14,700/1.04^2 + $14,700/1.04^3 + $14,700/1.04^4 + $14,700/1.04^5 + $14,700/1.04^6 + $14,700/1.04^7 + $14,700/1.04^8 + $14,700/1.04^9 = $27,904.37

b) The IRR is the interest rate that makes the NPV of the project equal to zero. The IRR for this project is:

0 = -$81,395 + $14,700/(1 + IRR) + $14,700/(1 + IRR)^2 + $14,700/(1 + IRR)^3 + $14,700/(1 + IRR)^4 + $14,700/(1 + IRR)^5 + $14,700/(1 + IRR)^6 + $14,700/(1 + IRR)^7 + $14,700/(1 + IRR)^8 + $14,700/(1 + IRR)^9

IRR = 11.00%


Related Solutions

A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a)...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a) If the required return is 13 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.   ...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.    What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations. Round the final answer to 2 decimal places.)      NPV $       At a required return of 8 percent, should the firm accept this project? Accept or Reject    What is the NPV for the project if the required return is 20 percent? (Do not...
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a....
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a. If the required return is 19 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a....
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.   ...
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.    Required: (a) If the required return is 9 percent, what is the NPV for this project?    (b) Determine the IRR for this project. rev: 09_18_2012, 09_26_2017_QC_C
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.   ...
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.    a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a....
A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? What is the NPV for the project if the required return is 20%? At a required return of 20% should the firm accept this project? At what discount rate would you be indifferent between accepting the project and rejecting it? 
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required:...
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required: (a) If the required return is 10 percent, what is the NPV for this project? (b) Determine the IRR for this project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT