In: Finance
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today. |
a. If the required return is 14 percent, what is the NPV for this project? |
b. Determine the IRR for this project. |
By Interpolation Method | |||||
IRR | = | Lowest Discount Rate + [NPV at Lower rate * (Higher Rate - Lower Rate) / (NPV at Lower Rate - NPV at Higher Rate)] | |||
= | 9% + [3814.96 * (14%-9%) / (3814.96 -(-12820.79)] | ||||
= | 9% +[3814.96 *5% /16635.75] | ||||
= | 9% + 1.15% | ||||
= | 10.15% |