Question

In: Finance

A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a....

A project that provides annual cash flows of $2,620 for eight years costs $9,430 today.
a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
c. At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Solutions

Expert Solution

Solution :

a. At a required return of 8 percent, the NPV of the project = $ 5,626.19

b. At a required return of 24 percent, the NPV of the project = - $ 466.40

c. The discount rate at which one would be indifferent between accepting the project and rejecting is the Internal Rate of return.

The Internal Rate of return (IRR) of the project = 22.19 %

Please find the attached screenshots of the excel sheet containing the detailed calculation for the solution.


Related Solutions

A project that provides annual cash flows of $17673 for eight years costs $80339 today. What...
A project that provides annual cash flows of $17673 for eight years costs $80339 today. What is the NPV for the project if the required return is 19 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16))
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a)...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a) If the required return is 13 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A)...
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A) If the required return is 4 percent, what is the NPV for this project? B)Determine the IRR for this project.
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.   ...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.    What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations. Round the final answer to 2 decimal places.)      NPV $       At a required return of 8 percent, should the firm accept this project? Accept or Reject    What is the NPV for the project if the required return is 20 percent? (Do not...
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a....
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a. If the required return is 19 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a....
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.   ...
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.    Required: (a) If the required return is 9 percent, what is the NPV for this project?    (b) Determine the IRR for this project. rev: 09_18_2012, 09_26_2017_QC_C
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.   ...
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.    a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? What is the NPV for the project if the required return is 20%? At a required return of 20% should the firm accept this project? At what discount rate would you be indifferent between accepting the project and rejecting it? 
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT